Refresh data
Refresh data

2 years ago

on Monday, May 15th 2023, 6:30:00 pm
Work Sanctioned
जनपद पौड़ी गढ़वाल के विधानसभा क्षेत्र लैन्सडौन के विकासखण्ड रिखणीखाल के अन्तर्गत किल्बोखाल से टकोलीखाल मोटर मार्ग के किमी0 1.00 से 18.00 तक में सुधारीकरण आदि का कार्य।

2 years ago

on Friday, June 30th 2023, 6:41:19 am

Technical Sanction
of ₹ 419.21 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 4076/12(186)YATA-PAURI/2023

2 years ago

on Tuesday, August 29th 2023, 6:30:00 pm
0.02%
Financial Progress

1st Expenditure
of ₹ 10349 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 419.21Lacs )

2 years ago

on Monday, September 11th 2023, 6:30:00 pm
20%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Thursday, September 28th 2023, 6:30:00 pm
12.29%
Financial Progress

2nd Expenditure
of ₹ 5139682 (51.40 Lacs ) done.
Cummulative ₹ 51.50Lacs ( against 419.21Lacs )

2 years ago

on Wednesday, November 8th 2023, 6:30:00 pm
25%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Tuesday, December 12th 2023, 6:30:00 pm
30%

Physical Progress
Physical Progress Reported at 3rd time

2 years ago

on Thursday, December 14th 2023, 6:30:00 pm
35%

Physical Progress
Physical Progress Reported at 4th time

2 years ago

on Tuesday, February 6th 2024, 6:30:00 pm
18.51%
Financial Progress

3rd Expenditure
of ₹ 2611300 (26.11 Lacs ) done.
Cummulative ₹ 77.61Lacs ( against 419.21Lacs )

2 years ago

on Friday, February 9th 2024, 6:30:00 pm
31.76%
Financial Progress

4th Expenditure
of ₹ 5551003 (55.51 Lacs ) done.
Cummulative ₹ 133.12Lacs ( against 419.21Lacs )

2 years ago

on Tuesday, February 27th 2024, 6:30:00 pm
31.76%
Financial Progress

5th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 133.12Lacs ( against 419.21Lacs )

2 years ago

on Sunday, March 24th 2024, 6:30:00 pm
63.87%
Financial Progress

6th Expenditure
of ₹ 13463586 (134.64 Lacs ) done.
Cummulative ₹ 267.76Lacs ( against 419.21Lacs )

2 years ago

on Wednesday, March 27th 2024, 6:30:00 pm
70%

Physical Progress
Physical Progress Reported at 5th time

a year ago

on Tuesday, May 7th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 6th time

a year ago

on Sunday, May 19th 2024, 6:30:00 pm
78.06%
Financial Progress

7th Expenditure
of ₹ 5947972 (59.48 Lacs ) done.
Cummulative ₹ 327.24Lacs ( against 419.21Lacs )

a year ago

on Sunday, May 19th 2024, 6:30:00 pm
85.13%
Financial Progress

8th Expenditure
of ₹ 2963851 (29.64 Lacs ) done.
Cummulative ₹ 356.88Lacs ( against 419.21Lacs )

a year ago

on Wednesday, May 29th 2024, 6:30:00 pm
85.13%
Financial Progress

9th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 356.88Lacs ( against 419.21Lacs )

a year ago

on Thursday, June 13th 2024, 5:40:57 am
<span class="4">Picture Id:43750</span>
PWD Uttarakahnd
Photo (ID 43750) from Site Received
Uploader : Vipin Dhuliya, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 0.400
Remark : pc work complete

a year ago

on Thursday, June 13th 2024, 6:10:51 am
<span class="4">Picture Id:43751</span>
PWD Uttarakahnd
Photo (ID 43751) from Site Received
Uploader : Vipin Dhuliya, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 0.700
Remark : pc work complete

a year ago

on Thursday, June 13th 2024, 6:13:11 am
<span class="4">Picture Id:43758</span>
PWD Uttarakahnd
Photo (ID 43758) from Site Received
Uploader : Vipin Dhuliya, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 1.800
Remark : PC work complete

a year ago

on Thursday, June 13th 2024, 6:18:10 am
<span class="4">Picture Id:43779</span>
PWD Uttarakahnd
Photo (ID 43779) from Site Received
Uploader : Vipin Dhuliya, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 3.200
Remark : PC work complete

a year ago

on Sunday, July 28th 2024, 6:30:00 pm
96.64%
Financial Progress

10th Expenditure
of ₹ 4824685 (48.25 Lacs ) done.
Cummulative ₹ 405.12Lacs ( against 419.21Lacs )

a year ago

on Sunday, September 8th 2024, 6:30:00 pm
96.79%
Financial Progress

13th Expenditure
of ₹ 42480 (0.42 Lacs ) done.
Cummulative ₹ 405.75Lacs ( against 419.21Lacs )

a year ago

on Sunday, September 8th 2024, 6:30:00 pm
96.66%
Financial Progress

11th Expenditure
of ₹ 9912 (0.10 Lacs ) done.
Cummulative ₹ 405.22Lacs ( against 419.21Lacs )

a year ago

on Sunday, September 8th 2024, 6:30:00 pm
96.69%
Financial Progress

12th Expenditure
of ₹ 9912 (0.10 Lacs ) done.
Cummulative ₹ 405.32Lacs ( against 419.21Lacs )

a year ago

on Monday, September 9th 2024, 6:30:00 pm
96.81%
Financial Progress

14th Expenditure
of ₹ 9912 (0.10 Lacs ) done.
Cummulative ₹ 405.85Lacs ( against 419.21Lacs )

a year ago

on Thursday, September 12th 2024, 6:30:00 pm
97.34%
Financial Progress

15th Expenditure
of ₹ 223020 (2.23 Lacs ) done.
Cummulative ₹ 408.08Lacs ( against 419.21Lacs )

a year ago

on Monday, October 14th 2024, 6:30:00 pm
97.38%
Financial Progress

16th Expenditure
of ₹ 16650 (0.17 Lacs ) done.
Cummulative ₹ 408.24Lacs ( against 419.21Lacs )

9 months ago

on Sunday, January 19th 2025, 6:30:00 pm
98.95%
Financial Progress

17th Expenditure
of ₹ 655299 (6.55 Lacs ) done.
Cummulative ₹ 414.80Lacs ( against 419.21Lacs )

8 months ago

on Wednesday, February 12th 2025, 6:30:00 pm
98.98%
Financial Progress

18th Expenditure
of ₹ 12463 (0.12 Lacs ) done.
Cummulative ₹ 414.92Lacs ( against 419.21Lacs )

7 months ago

on Sunday, March 16th 2025, 6:30:00 pm
99.80%
Financial Progress

19th Expenditure
of ₹ 344618 (3.45 Lacs ) done.
Cummulative ₹ 418.37Lacs ( against 419.21Lacs )

AI layer

AI Road
AI Bridge
10000 km
5000 mi
Unavailable