on Thursday, September 7th 2023, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद पौड़ी गढ़वाल के विधानसभा क्षेत्र लैन्सडौन के विकासखण्ड रिखणीखाल में कण्डलसेरा-डल्ला मोटर मार्ग के विस्तारीकरण का कार्य।(प्रथम चरण)।
on Thursday, December 7th 2023, 9:47:26 am
Technical Sanction
of ₹ 3 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 49(T.S.)/16C, Dated 07-12-2023
on Monday, March 25th 2024, 6:30:00 pm
57.27%
Financial Progress
1st Expenditure
of ₹ 171816 (1.72 Lacs ) done.
Cummulative ₹ 1.72Lacs ( against 3Lacs )
on Tuesday, May 14th 2024, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 1st time
on Saturday, June 1st 2024, 6:30:00 pm
70%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, June 19th 2024, 6:30:00 pm
94.60%
Financial Progress
2nd Expenditure
of ₹ 111974 (1.12 Lacs ) done.
Cummulative ₹ 2.84Lacs ( against 3Lacs )