on Thursday, March 14th 2024, 6:30:00 pm
Work Sanctioned
सड़क सुरक्षा मद के अन्तर्गत जनपद पौड़ी गढ़वाल के घट्टूगाड-सिलोगी-गुमखाल-लैन्सडौन-रिखणीखाल-बीरोंखाल राज्य मार्ग सं0-51 के किमी0 127.00 से 136.00 में क्रैश बैरियर का कार्य।
on Friday, June 7th 2024, 5:24:21 am
Technical Sanction
of ₹ 443.44 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1891/12(259) YATA-(LANSDOWNE)-PAURI/2024, DATE 07-06-2024
on Thursday, June 27th 2024, 6:30:00 pm
0.00%
Financial Progress
1st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 443.44Lacs )
on Friday, November 29th 2024, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, December 3rd 2024, 8:26:47 am
PWD UttarakahndPhoto (ID 60299) from Site Received
Uploader : Sonu Kumar, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 130.500
Remark : Road safety work at SH 51 under pd PWD Lansdowne
on Tuesday, December 17th 2024, 5:21:53 am
PWD UttarakahndPhoto (ID 61286) from Site Received
Uploader : Sonu Kumar, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : Km 129
Remark : Road safety work in progress at SH 51
on Wednesday, December 18th 2024, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 2nd time
on Friday, January 17th 2025, 6:31:04 am
PWD UttarakahndPhoto (ID 62867) from Site Received
Uploader : Sonu Kumar, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 128.250
Remark : Road safety work in progress at SH 51
on Friday, January 17th 2025, 9:15:13 am
PWD UttarakahndPhoto (ID 62908) from Site Received
Uploader : Sonu Kumar, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 2.800km
Remark : Wbm work in progress at simadi kanduli chhoti motor road
on Sunday, January 26th 2025, 6:30:00 pm
57.23%
Financial Progress
2nd Expenditure
of ₹ 25378751 (253.79 Lacs ) done.
Cummulative ₹ 253.79Lacs ( against 443.44Lacs )
on Thursday, February 6th 2025, 10:00:11 am
PWD UttarakahndPhoto (ID 64122) from Site Received
Uploader : Mohd Ikram , Additional Assistant Engineer Civil ,PD Lansdown
Landmark : Km-129
Remark : Ok
on Sunday, March 16th 2025, 6:30:00 pm
57.27%
Financial Progress
3rd Expenditure
of ₹ 18880 (0.19 Lacs ) done.
Cummulative ₹ 253.98Lacs ( against 443.44Lacs )
on Friday, March 28th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 3rd time
on Thursday, June 19th 2025, 6:30:00 pm
92.64%
Financial Progress
4th Expenditure
of ₹ 15680443 (156.80 Lacs ) done.
Cummulative ₹ 410.78Lacs ( against 443.44Lacs )
on Monday, July 14th 2025, 6:30:00 pm
97.41%
Financial Progress
5th Expenditure
of ₹ 2117176 (21.17 Lacs ) done.
Cummulative ₹ 431.95Lacs ( against 443.44Lacs )