6 months ago

on Friday, March 21st 2025, 6:30:00 pm
Work Sanctioned
नैनीडांडा-शंकरपुर मोटर मार्ग में सुधारीकरण का कार्य।

6 months ago

on Friday, March 28th 2025, 6:55:40 am

Technical Sanction
of ₹ 40 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE 144(TS)/16C dated 28-03-2025

4 months ago

on Sunday, May 18th 2025, 6:30:00 pm
10%

Physical Progress
Physical Progress Reported at 1st time

3 months ago

on Tuesday, June 24th 2025, 6:30:00 pm
50%

Physical Progress
Physical Progress Reported at 2nd time

3 months ago

on Wednesday, June 25th 2025, 6:30:00 pm
36.34%
Financial Progress

1st Expenditure
of ₹ 1453760 (14.54 Lacs ) done.
Cummulative ₹ 14.54Lacs ( against 40Lacs )

a month ago

on Monday, August 25th 2025, 6:30:00 pm
70.48%
Financial Progress

2nd Expenditure
of ₹ 1365260 (13.65 Lacs ) done.
Cummulative ₹ 28.19Lacs ( against 40Lacs )

12 days ago

on Wednesday, September 10th 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 3rd time