Refresh data
on Tuesday, November 5th 2024, 6:30:00 pm
Work Sanctioned
सड़क सुरक्षा मद के अन्तर्गत जनपद पौड़ी गढ़वाल में विकास खण्ड यमकेश्वर के अन्तर्गत राज्य मार्ग सं0-9 (स्व0 जगमोहन सिंह नेगी) के कि0मी0 12 से 30 तक क्रैश बैरियर का कार्य।
on Thursday, December 19th 2024, 7:42:52 am
Technical Sanction
of ₹ 452.55 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 6710(I)/12(288)yata/24
on Saturday, March 29th 2025, 6:30:00 pm
92.59%
Financial Progress
1st Expenditure
of ₹ 41902272 (419.02 Lacs ) done.
Cummulative ₹ 419.02Lacs ( against 452.55Lacs )
on Thursday, April 10th 2025, 6:30:00 pm
75%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, May 1st 2025, 6:30:00 pm
85%
Physical Progress
Physical Progress Reported at 2nd time
on Tuesday, June 3rd 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 3rd time
on Wednesday, July 30th 2025, 6:30:00 pm
99.15%
Financial Progress
2nd Expenditure
of ₹ 2970000 (29.70 Lacs ) done.
Cummulative ₹ 448.72Lacs ( against 452.55Lacs )