Work Sanctioned
मा0मुख्यमंत्री जी की घोषणा सं0-571/2015 के अन्तर्गत जनपद पौड़ी गढ़वाल के विधान सभा क्षेत्र कोटद्वार के अन्तर्गत कलालघाटी-मवाकोट मार्ग के मध्य मालन नदी पर 300 मी0 स्पान डबल लेन आर0सी0सी0 सेतु का निर्माण कार्य।
on Friday, February 19th 2016, 6:30:00 pm
Technical Sanction
of ₹ 46.16 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 582/1C
on Tuesday, October 31st 2017, 6:30:00 pm
16.75%
Financial Progress
1st Expenditure
of ₹ 773000 (7.73 Lacs ) done.
Cummulative ₹ 7.73Lacs ( against 46.16Lacs )
on Sunday, December 31st 2017, 6:30:00 pm
10.40%
Financial Progress
2nd Expenditure
of ₹ -293000 (-2.93 Lacs ) done.
Cummulative ₹ 4.80Lacs ( against 46.16Lacs )
on Wednesday, January 31st 2018, 6:30:00 pm
13.78%
Financial Progress
3rd Expenditure
of ₹ 156000 (1.56 Lacs ) done.
Cummulative ₹ 6.36Lacs ( against 46.16Lacs )
on Wednesday, February 28th 2018, 6:30:00 pm
15.97%
Financial Progress
4th Expenditure
of ₹ 101000 (1.01 Lacs ) done.
Cummulative ₹ 7.37Lacs ( against 46.16Lacs )
on Wednesday, October 31st 2018, 6:30:00 pm
33.30%
Financial Progress
5th Expenditure
of ₹ 800000 (8.00 Lacs ) done.
Cummulative ₹ 15.37Lacs ( against 46.16Lacs )
on Thursday, February 28th 2019, 6:30:00 pm
53.29%
Financial Progress
6th Expenditure
of ₹ 923000 (9.23 Lacs ) done.
Cummulative ₹ 24.60Lacs ( against 46.16Lacs )
on Sunday, May 31st 2020, 6:30:00 pm
65.47%
Financial Progress
7th Expenditure
of ₹ 562000 (5.62 Lacs ) done.
Cummulative ₹ 30.22Lacs ( against 46.16Lacs )
on Monday, August 31st 2020, 6:30:00 pm
78.25%
Financial Progress
8th Expenditure
of ₹ 590000 (5.90 Lacs ) done.
Cummulative ₹ 36.12Lacs ( against 46.16Lacs )
on Tuesday, March 29th 2022, 6:30:00 pm
81.43%
Financial Progress
9th Expenditure
of ₹ 147000 (1.47 Lacs ) done.
Cummulative ₹ 37.59Lacs ( against 46.16Lacs )
on Saturday, April 22nd 2023, 6:30:00 pm
81%
Physical Progress
Physical Progress Reported at 1st time