4 years ago

on Wednesday, September 1st 2021, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद पौड़ी गढ़वाल के विधान सभा क्षेत्र कोटद्वार के विकास खण्ड दुगड्डा के अन्तर्गत सिताबपुर, पदमपुर सुखरौ, सिम्मलचैड़ में विभिन्न सम्पर्क मार्गो का इण्टर लाॅकिंग टाईल्स द्वारा मार्ग का निर्माण।

4 years ago

on Monday, November 22nd 2021, 7:22:13 am

Technical Sanction
of ₹ 285.11 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 5584/12(91) yata dugadda pauri /2021

3 years ago

on Tuesday, March 29th 2022, 6:30:00 pm
4.81%
Financial Progress

1st Expenditure
of ₹ 1372000 (13.72 Lacs ) done.
Cummulative ₹ 13.72Lacs ( against 285.11Lacs )

3 years ago

on Wednesday, June 29th 2022, 6:30:00 pm
5.16%
Financial Progress

2nd Expenditure
of ₹ 98000 (0.98 Lacs ) done.
Cummulative ₹ 14.70Lacs ( against 285.11Lacs )

3 years ago

on Thursday, September 29th 2022, 6:30:00 pm
5.59%
Financial Progress

3rd Expenditure
of ₹ 124000 (1.24 Lacs ) done.
Cummulative ₹ 15.94Lacs ( against 285.11Lacs )

3 years ago

on Sunday, October 30th 2022, 6:30:00 pm
25.82%
Financial Progress

4th Expenditure
of ₹ 5768000 (57.68 Lacs ) done.
Cummulative ₹ 73.62Lacs ( against 285.11Lacs )

3 years ago

on Tuesday, November 29th 2022, 6:30:00 pm
26.17%
Financial Progress

5th Expenditure
of ₹ 100000 (1.00 Lacs ) done.
Cummulative ₹ 74.62Lacs ( against 285.11Lacs )

3 years ago

on Friday, December 30th 2022, 6:30:00 pm
26.92%
Financial Progress

6th Expenditure
of ₹ 213000 (2.13 Lacs ) done.
Cummulative ₹ 76.75Lacs ( against 285.11Lacs )

3 years ago

on Tuesday, January 3rd 2023, 6:30:00 pm
30%

Physical Progress
Physical Progress Reported at 1st time

3 years ago

on Monday, January 30th 2023, 6:30:00 pm
33.00%
Financial Progress

7th Expenditure
of ₹ 1734000 (17.34 Lacs ) done.
Cummulative ₹ 94.09Lacs ( against 285.11Lacs )

3 years ago

on Monday, February 27th 2023, 6:30:00 pm
33.52%
Financial Progress

8th Expenditure
of ₹ 147000 (1.47 Lacs ) done.
Cummulative ₹ 95.56Lacs ( against 285.11Lacs )

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
44.26%
Financial Progress

9th Expenditure
of ₹ 3062000 (30.62 Lacs ) done.
Cummulative ₹ 126.18Lacs ( against 285.11Lacs )

2 years ago

on Saturday, April 22nd 2023, 6:30:00 pm
53%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Thursday, June 29th 2023, 6:30:00 pm
50.70%
Financial Progress

10th Expenditure
of ₹ 1838000 (18.38 Lacs ) done.
Cummulative ₹ 144.56Lacs ( against 285.11Lacs )

2 years ago

on Friday, June 30th 2023, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 3rd time

2 years ago

on Tuesday, August 29th 2023, 6:30:00 pm
50.86%
Financial Progress

11th Expenditure
of ₹ 45000 (0.45 Lacs ) done.
Cummulative ₹ 145.01Lacs ( against 285.11Lacs )

2 years ago

on Friday, September 29th 2023, 6:30:00 pm
55.15%
Financial Progress

12th Expenditure
of ₹ 1222000 (12.22 Lacs ) done.
Cummulative ₹ 157.23Lacs ( against 285.11Lacs )

2 years ago

on Friday, September 29th 2023, 6:30:00 pm
95%

Physical Progress
Physical Progress Reported at 4th time

2 years ago

on Monday, October 30th 2023, 6:30:00 pm
55.28%
Financial Progress

13th Expenditure
of ₹ 38000 (0.38 Lacs ) done.
Cummulative ₹ 157.61Lacs ( against 285.11Lacs )

2 years ago

on Saturday, December 30th 2023, 6:30:00 pm
55.46%
Financial Progress

14th Expenditure
of ₹ 50000 (0.50 Lacs ) done.
Cummulative ₹ 158.11Lacs ( against 285.11Lacs )

2 years ago

on Wednesday, February 28th 2024, 6:30:00 pm
56.56%
Financial Progress

15th Expenditure
of ₹ 316000 (3.16 Lacs ) done.
Cummulative ₹ 161.27Lacs ( against 285.11Lacs )

2 years ago

on Tuesday, March 5th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 5th time

a year ago

on Saturday, March 30th 2024, 6:30:00 pm
59.93%
Financial Progress

17th Expenditure
of ₹ 959000 (9.59 Lacs ) done.
Cummulative ₹ 170.86Lacs ( against 285.11Lacs )

a year ago

on Saturday, March 30th 2024, 6:30:00 pm
56.56%
Financial Progress

16th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 161.27Lacs ( against 285.11Lacs )

6 months ago

on Monday, March 17th 2025, 6:30:00 pm
60.36%
Financial Progress

18th Expenditure
of ₹ 122643 (1.23 Lacs ) done.
Cummulative ₹ 172.09Lacs ( against 285.11Lacs )