2 years ago

on Thursday, October 26th 2023, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद पौड़ी गढ़वाल के विधान सभा क्षेत्र यमकेश्वर के अन्तर्गत ताछला मोटर मार्ग का निर्माण कार्य (द्वितीय चरण स्टेज प्रथम)।

2 years ago

on Sunday, February 18th 2024, 6:30:00 pm
0.17%
Financial Progress

1st Expenditure
of ₹ 26000 (0.26 Lacs ) done.
Cummulative ₹ 0.26Lacs ( against 149.59Lacs )

2 years ago

on Monday, February 26th 2024, 10:35:47 am

Technical Sanction
of ₹ 149.59 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 9346/1040 YATA-12/23

a year ago

on Tuesday, April 30th 2024, 6:30:00 pm
35%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Sunday, May 19th 2024, 6:30:00 pm
0.44%
Financial Progress

2nd Expenditure
of ₹ 40023 (0.40 Lacs ) done.
Cummulative ₹ 0.66Lacs ( against 149.59Lacs )

a year ago

on Sunday, June 16th 2024, 6:30:00 pm
22.03%
Financial Progress

3rd Expenditure
of ₹ 3228736 (32.29 Lacs ) done.
Cummulative ₹ 32.95Lacs ( against 149.59Lacs )

a year ago

on Friday, June 28th 2024, 6:30:00 pm
22.96%
Financial Progress

4th Expenditure
of ₹ 140332 (1.40 Lacs ) done.
Cummulative ₹ 34.35Lacs ( against 149.59Lacs )

a year ago

on Thursday, October 24th 2024, 6:30:00 pm
34.90%
Financial Progress

5th Expenditure
of ₹ 1785035 (17.85 Lacs ) done.
Cummulative ₹ 52.20Lacs ( against 149.59Lacs )

a year ago

on Friday, October 25th 2024, 6:30:00 pm
60%

Physical Progress
Physical Progress Reported at 2nd time

8 months ago

on Thursday, January 30th 2025, 6:30:00 pm
49.14%
Financial Progress

6th Expenditure
of ₹ 2130000 (21.30 Lacs ) done.
Cummulative ₹ 73.50Lacs ( against 149.59Lacs )

6 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
49.14%
Financial Progress

7th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 73.50Lacs ( against 149.59Lacs )

6 months ago

on Sunday, March 30th 2025, 6:30:00 pm
50.01%
Financial Progress

8th Expenditure
of ₹ 130626 (1.31 Lacs ) done.
Cummulative ₹ 74.81Lacs ( against 149.59Lacs )

3 months ago

on Sunday, June 29th 2025, 6:30:00 pm
57.16%
Financial Progress

9th Expenditure
of ₹ 1070000 (10.70 Lacs ) done.
Cummulative ₹ 85.51Lacs ( against 149.59Lacs )

3 months ago

on Thursday, July 3rd 2025, 6:30:00 pm
65%

Physical Progress
Physical Progress Reported at 3rd time