Refresh data
Refresh data

a year ago

on Monday, December 11th 2023, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री जी की घोषणा सं0-333/2023 के अन्तर्गत जनपद पौड़ी गढ़वाल के विधान सभा कोटद्वार के विकास खण्ड दुगड्डा में लालपानी सनेह मार्ग पर चार स्थानों में पुलिया का निर्माण कार्य।

a year ago

on Thursday, February 1st 2024, 11:34:48 am

Technical Sanction
of ₹ 369.6 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 495/12(234) YATA-DUGADDA-PAURI/23

a year ago

on Sunday, February 18th 2024, 6:30:00 pm
0.02%
Financial Progress

1st Expenditure
of ₹ 9000 (0.09 Lacs ) done.
Cummulative ₹ 0.09Lacs ( against 369.6Lacs )

a year ago

on Saturday, March 30th 2024, 6:30:00 pm
8.58%
Financial Progress

2nd Expenditure
of ₹ 3163000 (31.63 Lacs ) done.
Cummulative ₹ 31.72Lacs ( against 369.6Lacs )

10 months ago

on Tuesday, April 30th 2024, 6:30:00 pm
20%

Physical Progress
Physical Progress Reported at 1st time

9 months ago

on Monday, May 20th 2024, 10:09:49 pm
<span class="4">Picture Id:39436</span>
PWD Uttarakahnd
Photo (ID 39436) from Site Received
Uploader : Santosh Kumar, Additional Assistant Engineer Civil ,CD Dugadda
Landmark : C/O 11 mtr span bridge raft at ch 5.450
Remark : C/o 11 mtr span bridge in kotdware CDPWD DUGADDA

9 months ago

on Thursday, May 30th 2024, 6:30:00 pm
16.17%
Financial Progress

3rd Expenditure
of ₹ 2805542 (28.06 Lacs ) done.
Cummulative ₹ 59.78Lacs ( against 369.6Lacs )

9 months ago

on Thursday, May 30th 2024, 6:30:00 pm
30%

Physical Progress
Physical Progress Reported at 2nd time

9 months ago

on Friday, June 7th 2024, 7:37:20 am
<span class="4">Picture Id:42080</span>
PWD Uttarakahnd
Photo (ID 42080) from Site Received
Uploader : Santosh Kumar, Additional Assistant Engineer Civil ,CD Dugadda
Landmark : Km 5.225 of sidhbali kumbhichowre saneh motor
Remark : Raft concreting in 10 mtr bridge

9 months ago

on Friday, June 14th 2024, 6:30:00 pm
31.04%
Financial Progress

4th Expenditure
of ₹ 5494753 (54.95 Lacs ) done.
Cummulative ₹ 114.72Lacs ( against 369.6Lacs )

8 months ago

on Wednesday, June 26th 2024, 6:30:00 pm
60%

Physical Progress
Physical Progress Reported at 3rd time

8 months ago

on Friday, June 28th 2024, 6:30:00 pm
39.28%
Financial Progress

5th Expenditure
of ₹ 3046170 (30.46 Lacs ) done.
Cummulative ₹ 145.18Lacs ( against 369.6Lacs )

7 months ago

on Monday, August 12th 2024, 6:30:00 pm
39.33%
Financial Progress

6th Expenditure
of ₹ 18829 (0.19 Lacs ) done.
Cummulative ₹ 145.37Lacs ( against 369.6Lacs )

5 months ago

on Wednesday, October 2nd 2024, 6:30:00 pm
65%

Physical Progress
Physical Progress Reported at 4th time

5 months ago

on Thursday, October 17th 2024, 6:30:00 pm
39.40%
Financial Progress

7th Expenditure
of ₹ 25688 (0.26 Lacs ) done.
Cummulative ₹ 145.63Lacs ( against 369.6Lacs )

4 months ago

on Tuesday, October 22nd 2024, 12:52:49 am
<span class="4">Picture Id:57696</span>
PWD Uttarakahnd
Photo (ID 57696) from Site Received
Uploader : Santosh Kumar, Additional Assistant Engineer Civil ,CD Dugadda
Landmark : C/o 13 mtr span puliya in lalpani kotdware Km 5.700
Remark : C/o 13 mtr span puliya

4 months ago

on Monday, October 28th 2024, 1:55:35 am
<span class="4">Picture Id:58315</span>
PWD Uttarakahnd
Photo (ID 58315) from Site Received
Uploader : Santosh Kumar, Additional Assistant Engineer Civil ,CD Dugadda
Landmark : C/o 13 mtr span puliya in lalpani saneh kotdware
Remark : C/O 13 mtr span puliya in lalpani kotdware

4 months ago

on Monday, October 28th 2024, 1:59:28 am
<span class="4">Picture Id:58316</span>
PWD Uttarakahnd
Photo (ID 58316) from Site Received
Uploader : Santosh Kumar, Additional Assistant Engineer Civil ,CD Dugadda
Landmark : Ch 5.700
Remark : C/O 13 mtr span bridge in saneh lalpani

3 months ago

on Monday, November 25th 2024, 5:53:48 am
<span class="4">Picture Id:59476</span>
PWD Uttarakahnd
Photo (ID 59476) from Site Received
Uploader : Santosh Kumar, Additional Assistant Engineer Civil ,CD Dugadda
Landmark : Km 5.225
Remark : C/o 10 mtr lalpani puliya

3 months ago

on Tuesday, December 17th 2024, 6:30:00 pm
45.96%
Financial Progress

8th Expenditure
of ₹ 2423538 (24.24 Lacs ) done.
Cummulative ₹ 169.87Lacs ( against 369.6Lacs )

2 months ago

on Thursday, January 16th 2025, 6:30:00 pm
46.72%
Financial Progress

9th Expenditure
of ₹ 281462 (2.81 Lacs ) done.
Cummulative ₹ 172.68Lacs ( against 369.6Lacs )

a month ago

on Sunday, February 2nd 2025, 6:30:00 pm
85%

Physical Progress
Physical Progress Reported at 5th time

AI layer

AI Road
AI Bridge
10000 km
5000 mi
Unavailable