15 years ago

on Thursday, March 24th 2011, 6:30:00 pm
Work Sanctioned
fवकासखण्ड थलीसैंण के अन्तर्गत सेरामाण्डे सम्पर्क मार्ग पर लौह सेतु का fनर्माण कार्य।

12 years ago

on Friday, February 28th 2014, 6:30:00 pm
89.20%
Financial Progress

1st Expenditure
of ₹ 289000 (2.89 Lacs ) done.
Cummulative ₹ 2.89Lacs ( against 3.24Lacs )

11 years ago

on Saturday, February 28th 2015, 6:30:00 pm
92.28%
Financial Progress

2nd Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 2.99Lacs ( against 3.24Lacs )

10 years ago

on Monday, February 29th 2016, 6:30:00 pm
100.00%
Financial Progress

3rd Expenditure
of ₹ 25000 (0.25 Lacs ) done.
Cummulative ₹ 3.24Lacs ( against 3.24Lacs )

a year ago

on Wednesday, April 24th 2024, 6:30:00 pm
10%

Physical Progress
Physical Progress Reported at 1st time