Work Sanctioned
जनपद पौड़ी गढ़वाल के विधानसभा क्षेत्र श्रीनगर के विकासखण्ड थलीसैंण के अन्तर्गत मंज्यूर सम्पर्क मार्ग का नव निर्माण कार्य (द्वितीय चरण स्टेज-।)
on Wednesday, September 15th 2021, 4:03:34 am
Technical Sanction
of ₹ 23.03 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE EE 1375/18C dated 15/09/2021 OF Amount 23.03 lac
on Sunday, January 30th 2022, 6:30:00 pm
28.44%
Financial Progress
1st Expenditure
of ₹ 655000 (6.55 Lacs ) done.
Cummulative ₹ 6.55Lacs ( against 23.03Lacs )
on Sunday, March 27th 2022, 6:30:00 pm
93.01%
Financial Progress
2nd Expenditure
of ₹ 1487000 (14.87 Lacs ) done.
Cummulative ₹ 21.42Lacs ( against 23.03Lacs )
on Thursday, December 8th 2022, 6:43:13 am
PWD UttarakahndPhoto (ID 13619) from Site Received
Uploader : Devraj Singh Pokhriyal, Additional Assistant Engineer Civil ,CD Uttarkashi
Landmark : 0/0
Remark : Information board at Manjyur MR 2nd Phase Stage 1
on Monday, December 26th 2022, 6:30:00 pm
105.25%
Financial Progress
3rd Expenditure
of ₹ 282000 (2.82 Lacs ) done.
Cummulative ₹ 24.24Lacs ( against 23.03Lacs )
on Wednesday, December 28th 2022, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Monday, January 30th 2023, 6:30:00 pm
108.73%
Financial Progress
4th Expenditure
of ₹ 80000 (0.80 Lacs ) done.
Cummulative ₹ 25.04Lacs ( against 23.03Lacs )
on Monday, March 25th 2024, 6:30:00 pm
100.00%
Financial Progress
5th Expenditure
of ₹ -201000 (-2.01 Lacs ) done.
Cummulative ₹ 23.03Lacs ( against 23.03Lacs )