4 years ago

on Wednesday, July 21st 2021, 6:30:00 pm
Work Sanctioned
जनपद पौड़ी गढ़वाल के विधानसभा क्षेत्र श्रीनगर के विकासखण्ड थलीसैंण के अन्तर्गत मंज्यूर सम्पर्क मार्ग का नव निर्माण कार्य (द्वितीय चरण स्टेज-।)

4 years ago

on Wednesday, September 15th 2021, 4:03:34 am

Technical Sanction
of ₹ 23.03 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. TS VIDE EE 1375/18C dated 15/09/2021 OF Amount 23.03 lac

4 years ago

on Sunday, January 30th 2022, 6:30:00 pm
28.44%
Financial Progress

1st Expenditure
of ₹ 655000 (6.55 Lacs ) done.
Cummulative ₹ 6.55Lacs ( against 23.03Lacs )

4 years ago

on Sunday, March 27th 2022, 6:30:00 pm
93.01%
Financial Progress

2nd Expenditure
of ₹ 1487000 (14.87 Lacs ) done.
Cummulative ₹ 21.42Lacs ( against 23.03Lacs )

3 years ago

on Thursday, December 8th 2022, 6:43:13 am
<span class="4">Picture Id:13619</span>
PWD Uttarakahnd
Photo (ID 13619) from Site Received
Uploader : Devraj Singh Pokhriyal, Additional Assistant Engineer Civil ,CD Uttarkashi
Landmark : 0/0
Remark : Information board at Manjyur MR 2nd Phase Stage 1

3 years ago

on Monday, December 26th 2022, 6:30:00 pm
105.25%
Financial Progress

3rd Expenditure
of ₹ 282000 (2.82 Lacs ) done.
Cummulative ₹ 24.24Lacs ( against 23.03Lacs )

3 years ago

on Wednesday, December 28th 2022, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 1st time

3 years ago

on Monday, January 30th 2023, 6:30:00 pm
108.73%
Financial Progress

4th Expenditure
of ₹ 80000 (0.80 Lacs ) done.
Cummulative ₹ 25.04Lacs ( against 23.03Lacs )

2 years ago

on Monday, March 25th 2024, 6:30:00 pm
100.00%
Financial Progress

5th Expenditure
of ₹ -201000 (-2.01 Lacs ) done.
Cummulative ₹ 23.03Lacs ( against 23.03Lacs )