a year ago

on Thursday, August 22nd 2024, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री घोषणा संख्या- 269/2022 (श्रीनगर विधानसभा के अन्तर्गत कच्ची सडको का डामरीकरण (50 किमी0) की स्वीकृति प्रदान की जायेगी) के अन्तर्गत जनपद पौडी गढवाल के विधानसभा क्षेत्र श्रीनगर के विकासखण्ड थलीसैंण के अन्तर्गत मैखुली-देवराडी-गणतखाल मोटर मार्ग का सुधार एवं डामरीकरण का कार्य ।

10 months ago

on Monday, December 2nd 2024, 6:30:00 pm
8.73%
Financial Progress

1st Expenditure
of ₹ 2015022 (20.15 Lacs ) done.
Cummulative ₹ 20.15Lacs ( against 230.93Lacs )

10 months ago

on Monday, December 9th 2024, 6:30:00 pm
8.73%
Financial Progress

2nd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 20.15Lacs ( against 230.93Lacs )

9 months ago

on Wednesday, January 15th 2025, 6:30:00 pm
14.64%
Financial Progress

3rd Expenditure
of ₹ 1365883 (13.66 Lacs ) done.
Cummulative ₹ 33.81Lacs ( against 230.93Lacs )

8 months ago

on Monday, February 3rd 2025, 6:30:00 pm
34.57%
Financial Progress

4th Expenditure
of ₹ 4601438 (46.01 Lacs ) done.
Cummulative ₹ 79.82Lacs ( against 230.93Lacs )

7 months ago

on Wednesday, February 19th 2025, 6:30:00 pm
25%

Physical Progress
Physical Progress Reported at 1st time

6 months ago

on Monday, March 17th 2025, 6:30:00 pm
35.09%
Financial Progress

5th Expenditure
of ₹ 121537 (1.22 Lacs ) done.
Cummulative ₹ 81.04Lacs ( against 230.93Lacs )

6 months ago

on Wednesday, March 19th 2025, 6:30:00 pm
34.57%
Financial Progress

6th Expenditure
of ₹ -121537 (-1.22 Lacs ) done.
Cummulative ₹ 79.82Lacs ( against 230.93Lacs )

6 months ago

on Thursday, March 20th 2025, 6:30:00 pm
65.51%
Financial Progress

8th Expenditure
of ₹ 6294643 (62.95 Lacs ) done.
Cummulative ₹ 151.27Lacs ( against 230.93Lacs )

6 months ago

on Thursday, March 20th 2025, 6:30:00 pm
38.25%
Financial Progress

7th Expenditure
of ₹ 850510 (8.51 Lacs ) done.
Cummulative ₹ 88.33Lacs ( against 230.93Lacs )

6 months ago

on Monday, April 7th 2025, 6:30:00 pm
77%

Physical Progress
Physical Progress Reported at 2nd time

5 months ago

on Sunday, April 20th 2025, 6:01:01 am
<span class="4">Picture Id:67705</span>
PWD Uttarakahnd
Photo (ID 67705) from Site Received
Uploader : Tasleem Ahamad, Assistant Engineer Civil ,CD Baijro
Landmark : 22.175 km
Remark : pc work,crash barrier and drainage system etc complete

5 months ago

on Sunday, May 4th 2025, 6:30:00 pm
95%

Physical Progress
Physical Progress Reported at 3rd time

4 months ago

on Tuesday, May 27th 2025, 6:30:00 pm
79.18%
Financial Progress

9th Expenditure
of ₹ 3157618 (31.58 Lacs ) done.
Cummulative ₹ 182.85Lacs ( against 230.93Lacs )

3 months ago

on Friday, July 4th 2025, 6:30:00 pm
90.64%
Financial Progress

10th Expenditure
of ₹ 2646698 (26.47 Lacs ) done.
Cummulative ₹ 209.32Lacs ( against 230.93Lacs )

8 days ago

on Tuesday, September 23rd 2025, 6:30:00 pm
91.02%
Financial Progress

14th Expenditure
of ₹ 27140 (0.27 Lacs ) done.
Cummulative ₹ 210.19Lacs ( against 230.93Lacs )

8 days ago

on Tuesday, September 23rd 2025, 6:30:00 pm
90.90%
Financial Progress

13th Expenditure
of ₹ 1770 (0.02 Lacs ) done.
Cummulative ₹ 209.91Lacs ( against 230.93Lacs )

8 days ago

on Tuesday, September 23rd 2025, 6:30:00 pm
90.89%
Financial Progress

12th Expenditure
of ₹ 33040 (0.33 Lacs ) done.
Cummulative ₹ 209.90Lacs ( against 230.93Lacs )

8 days ago

on Tuesday, September 23rd 2025, 6:30:00 pm
90.75%
Financial Progress

11th Expenditure
of ₹ 24780 (0.25 Lacs ) done.
Cummulative ₹ 209.57Lacs ( against 230.93Lacs )

6 days ago

on Thursday, September 25th 2025, 6:30:00 pm
91.02%
Financial Progress

15th Expenditure
of ₹ 1770 (0.02 Lacs ) done.
Cummulative ₹ 210.20Lacs ( against 230.93Lacs )