Work Sanctioned
मा0 मुख्यमंत्री घोषणा संख्या- 269/2022 (श्रीनगर विधानसभा के अन्तर्गत कच्ची सडको का डामरीकरण (50 किमी0) की स्वीकृति प्रदान की जायेगी) के अन्तर्गत जनपद पौडी गढवाल के विधानसभा क्षेत्र श्रीनगर के विकासखण्ड थलीसैंण के अन्तर्गत मैखुली-देवराडी-गणतखाल मोटर मार्ग का सुधार एवं डामरीकरण का कार्य ।
on Monday, December 2nd 2024, 6:30:00 pm
8.73%
Financial Progress
1st Expenditure
of ₹ 2015022 (20.15 Lacs ) done.
Cummulative ₹ 20.15Lacs ( against 230.93Lacs )
on Monday, December 9th 2024, 6:30:00 pm
8.73%
Financial Progress
2nd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 20.15Lacs ( against 230.93Lacs )
on Wednesday, January 15th 2025, 6:30:00 pm
14.64%
Financial Progress
3rd Expenditure
of ₹ 1365883 (13.66 Lacs ) done.
Cummulative ₹ 33.81Lacs ( against 230.93Lacs )
on Monday, February 3rd 2025, 6:30:00 pm
34.57%
Financial Progress
4th Expenditure
of ₹ 4601438 (46.01 Lacs ) done.
Cummulative ₹ 79.82Lacs ( against 230.93Lacs )
on Wednesday, February 19th 2025, 6:30:00 pm
25%
Physical Progress
Physical Progress Reported at 1st time
on Monday, March 17th 2025, 6:30:00 pm
35.09%
Financial Progress
5th Expenditure
of ₹ 121537 (1.22 Lacs ) done.
Cummulative ₹ 81.04Lacs ( against 230.93Lacs )
on Wednesday, March 19th 2025, 6:30:00 pm
34.57%
Financial Progress
6th Expenditure
of ₹ -121537 (-1.22 Lacs ) done.
Cummulative ₹ 79.82Lacs ( against 230.93Lacs )
on Thursday, March 20th 2025, 6:30:00 pm
65.51%
Financial Progress
8th Expenditure
of ₹ 6294643 (62.95 Lacs ) done.
Cummulative ₹ 151.27Lacs ( against 230.93Lacs )
on Thursday, March 20th 2025, 6:30:00 pm
38.25%
Financial Progress
7th Expenditure
of ₹ 850510 (8.51 Lacs ) done.
Cummulative ₹ 88.33Lacs ( against 230.93Lacs )
on Monday, April 7th 2025, 6:30:00 pm
77%
Physical Progress
Physical Progress Reported at 2nd time
on Sunday, April 20th 2025, 6:01:01 am
PWD UttarakahndPhoto (ID 67705) from Site Received
Uploader : Tasleem Ahamad, Assistant Engineer Civil ,CD Baijro
Landmark : 22.175 km
Remark : pc work,crash barrier and drainage system etc complete
on Sunday, May 4th 2025, 6:30:00 pm
95%
Physical Progress
Physical Progress Reported at 3rd time
on Tuesday, May 27th 2025, 6:30:00 pm
79.18%
Financial Progress
9th Expenditure
of ₹ 3157618 (31.58 Lacs ) done.
Cummulative ₹ 182.85Lacs ( against 230.93Lacs )
on Friday, July 4th 2025, 6:30:00 pm
90.64%
Financial Progress
10th Expenditure
of ₹ 2646698 (26.47 Lacs ) done.
Cummulative ₹ 209.32Lacs ( against 230.93Lacs )
on Tuesday, September 23rd 2025, 6:30:00 pm
91.02%
Financial Progress
14th Expenditure
of ₹ 27140 (0.27 Lacs ) done.
Cummulative ₹ 210.19Lacs ( against 230.93Lacs )
on Tuesday, September 23rd 2025, 6:30:00 pm
90.90%
Financial Progress
13th Expenditure
of ₹ 1770 (0.02 Lacs ) done.
Cummulative ₹ 209.91Lacs ( against 230.93Lacs )
on Tuesday, September 23rd 2025, 6:30:00 pm
90.89%
Financial Progress
12th Expenditure
of ₹ 33040 (0.33 Lacs ) done.
Cummulative ₹ 209.90Lacs ( against 230.93Lacs )
on Tuesday, September 23rd 2025, 6:30:00 pm
90.75%
Financial Progress
11th Expenditure
of ₹ 24780 (0.25 Lacs ) done.
Cummulative ₹ 209.57Lacs ( against 230.93Lacs )
on Thursday, September 25th 2025, 6:30:00 pm
91.02%
Financial Progress
15th Expenditure
of ₹ 1770 (0.02 Lacs ) done.
Cummulative ₹ 210.20Lacs ( against 230.93Lacs )