7 years ago

on Thursday, February 28th 2019, 6:30:00 pm
0.03%
Financial Progress

1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 373.87Lacs )

7 years ago

on Monday, March 4th 2019, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद चमोली के विधानसभा क्षेत्र बद्रीनाथ के विकासखण्ड दशोली दशोली में गोपेेश्वर मंदिर मार्ग से वैतरणी-सिरौखोमा-सिटुणा-बैरागना मोटर मार्ग का नवनिर्माण (द्वितीय चरण)

6 years ago

on Friday, August 16th 2019, 6:30:00 pm

Technical Sanction
of ₹ 290.63 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. CE Pauri letter no- 2009/7(557) Yata-Pauri/2019

6 years ago

on Monday, September 30th 2019, 6:30:00 pm
0.47%
Financial Progress

2nd Expenditure
of ₹ 165000 (1.65 Lacs ) done.
Cummulative ₹ 1.75Lacs ( against 373.87Lacs )

6 years ago

on Thursday, October 31st 2019, 6:30:00 pm
5.10%
Financial Progress

3rd Expenditure
of ₹ 1731000 (17.31 Lacs ) done.
Cummulative ₹ 19.06Lacs ( against 373.87Lacs )

6 years ago

on Saturday, November 30th 2019, 6:30:00 pm
9.11%
Financial Progress

4th Expenditure
of ₹ 1500000 (15.00 Lacs ) done.
Cummulative ₹ 34.06Lacs ( against 373.87Lacs )

6 years ago

on Friday, January 31st 2020, 6:30:00 pm
17.90%
Financial Progress

5th Expenditure
of ₹ 3285000 (32.85 Lacs ) done.
Cummulative ₹ 66.91Lacs ( against 373.87Lacs )

6 years ago

on Saturday, February 29th 2020, 6:30:00 pm
18.12%
Financial Progress

6th Expenditure
of ₹ 82000 (0.82 Lacs ) done.
Cummulative ₹ 67.73Lacs ( against 373.87Lacs )

5 years ago

on Sunday, May 31st 2020, 6:30:00 pm
18.46%
Financial Progress

7th Expenditure
of ₹ 129000 (1.29 Lacs ) done.
Cummulative ₹ 69.02Lacs ( against 373.87Lacs )

5 years ago

on Friday, July 31st 2020, 6:30:00 pm
32.05%
Financial Progress

8th Expenditure
of ₹ 5082000 (50.82 Lacs ) done.
Cummulative ₹ 119.84Lacs ( against 373.87Lacs )

5 years ago

on Monday, August 31st 2020, 6:30:00 pm
32.24%
Financial Progress

9th Expenditure
of ₹ 68000 (0.68 Lacs ) done.
Cummulative ₹ 120.52Lacs ( against 373.87Lacs )

5 years ago

on Saturday, October 31st 2020, 6:30:00 pm
37.25%
Financial Progress

10th Expenditure
of ₹ 1874000 (18.74 Lacs ) done.
Cummulative ₹ 139.26Lacs ( against 373.87Lacs )

5 years ago

on Monday, November 30th 2020, 6:30:00 pm
49.71%
Financial Progress

11th Expenditure
of ₹ 4660000 (46.60 Lacs ) done.
Cummulative ₹ 185.86Lacs ( against 373.87Lacs )

5 years ago

on Thursday, December 31st 2020, 6:30:00 pm
50.14%
Financial Progress

12th Expenditure
of ₹ 159000 (1.59 Lacs ) done.
Cummulative ₹ 187.45Lacs ( against 373.87Lacs )

5 years ago

on Sunday, February 28th 2021, 6:30:00 pm
62.10%
Financial Progress

13th Expenditure
of ₹ 4474000 (44.74 Lacs ) done.
Cummulative ₹ 232.19Lacs ( against 373.87Lacs )

4 years ago

on Tuesday, June 29th 2021, 6:30:00 pm
62.10%
Financial Progress

14th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 232.19Lacs ( against 373.87Lacs )

4 years ago

on Friday, July 30th 2021, 6:30:00 pm
67.73%
Financial Progress

15th Expenditure
of ₹ 2102503 (21.03 Lacs ) done.
Cummulative ₹ 253.22Lacs ( against 373.87Lacs )

4 years ago

on Tuesday, August 10th 2021, 6:30:00 pm
60%

Physical Progress
Physical Progress Reported at 1st time

4 years ago

on Monday, August 30th 2021, 6:30:00 pm
69.75%
Financial Progress

16th Expenditure
of ₹ 756846 (7.57 Lacs ) done.
Cummulative ₹ 260.78Lacs ( against 373.87Lacs )

4 years ago

on Wednesday, September 29th 2021, 6:30:00 pm
70.01%
Financial Progress

17th Expenditure
of ₹ 94945 (0.95 Lacs ) done.
Cummulative ₹ 261.73Lacs ( against 373.87Lacs )

4 years ago

on Friday, October 29th 2021, 6:30:00 pm
73.38%
Financial Progress

18th Expenditure
of ₹ 1263000 (12.63 Lacs ) done.
Cummulative ₹ 274.36Lacs ( against 373.87Lacs )

4 years ago

on Tuesday, February 22nd 2022, 6:30:00 pm
76.79%
Financial Progress

19th Expenditure
of ₹ 1273384 (12.73 Lacs ) done.
Cummulative ₹ 287.10Lacs ( against 373.87Lacs )

4 years ago

on Wednesday, March 30th 2022, 6:30:00 pm
95.44%
Financial Progress

20th Expenditure
of ₹ 6971969 (69.72 Lacs ) done.
Cummulative ₹ 356.82Lacs ( against 373.87Lacs )

a year ago

on Thursday, June 6th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time