on Sunday, August 28th 2022, 6:30:00 pm
Work Sanctioned
जिला योजना वर्ष 2022-23 के अन्तर्गत ग्रामसभा ईराणी के अन्तर्गत झींझीं गांव से प्राथमिक विद्यालय तक 600 मी0 सी0सी0 मार्ग का कार्य
on Friday, September 9th 2022, 6:48:40 am
Technical Sanction
of ₹ 3 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1790/16 C
on Thursday, December 8th 2022, 6:30:00 pm
30%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, April 19th 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, April 20th 2023, 6:30:00 pm
70%
Physical Progress
Physical Progress Reported at 3rd time
on Saturday, December 30th 2023, 6:30:00 pm
96.24%
Financial Progress
1st Expenditure
of ₹ 288725 (2.89 Lacs ) done.
Cummulative ₹ 2.89Lacs ( against 3Lacs )
on Monday, June 10th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 4th time