3 years ago

on Tuesday, September 13th 2022, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद चमोली के विधानसभा क्षेत्र बद्रीनाथ के विकासखण्ड जोशीमठ में गोविन्दघाट से गुरुद्वारा तक बाईपास मार्ग का सुधारीकरण एवं डामरीकरण कार्य

3 years ago

on Wednesday, September 28th 2022, 10:44:39 am

Technical Sanction
of ₹ 77.68 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. EE No- 2005/1 c dt- 28-09-2022

2 years ago

on Sunday, December 11th 2022, 6:30:00 pm
5%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
0.13%
Financial Progress

1st Expenditure
of ₹ 9900 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 77.68Lacs )

2 years ago

on Thursday, June 29th 2023, 6:30:00 pm
52.37%
Financial Progress

2nd Expenditure
of ₹ 4058006 (40.58 Lacs ) done.
Cummulative ₹ 40.68Lacs ( against 77.68Lacs )

2 years ago

on Saturday, August 12th 2023, 6:30:00 pm
70%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Friday, September 29th 2023, 6:30:00 pm
72.31%
Financial Progress

3rd Expenditure
of ₹ 1549342 (15.49 Lacs ) done.
Cummulative ₹ 56.17Lacs ( against 77.68Lacs )

a year ago

on Tuesday, January 30th 2024, 6:30:00 pm
72.39%
Financial Progress

4th Expenditure
of ₹ 6056 (0.06 Lacs ) done.
Cummulative ₹ 56.23Lacs ( against 77.68Lacs )

a year ago

on Tuesday, February 27th 2024, 6:30:00 pm
72.48%
Financial Progress

5th Expenditure
of ₹ 7316 (0.07 Lacs ) done.
Cummulative ₹ 56.31Lacs ( against 77.68Lacs )

a year ago

on Wednesday, March 27th 2024, 6:30:00 pm
84.88%
Financial Progress

6th Expenditure
of ₹ 962846 (9.63 Lacs ) done.
Cummulative ₹ 65.93Lacs ( against 77.68Lacs )

a year ago

on Thursday, April 4th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 3rd time

8 months ago

on Monday, August 12th 2024, 6:30:00 pm
88.09%
Financial Progress

7th Expenditure
of ₹ 249254 (2.49 Lacs ) done.
Cummulative ₹ 68.43Lacs ( against 77.68Lacs )

7 months ago

on Tuesday, September 24th 2024, 6:30:00 pm
88.28%
Financial Progress

8th Expenditure
of ₹ 15057 (0.15 Lacs ) done.
Cummulative ₹ 68.58Lacs ( against 77.68Lacs )

6 months ago

on Tuesday, October 15th 2024, 6:30:00 pm
88.51%
Financial Progress

9th Expenditure
of ₹ 17759 (0.18 Lacs ) done.
Cummulative ₹ 68.76Lacs ( against 77.68Lacs )

25 days ago

on Tuesday, March 18th 2025, 6:30:00 pm
88.86%
Financial Progress

10th Expenditure
of ₹ 27000 (0.27 Lacs ) done.
Cummulative ₹ 69.03Lacs ( against 77.68Lacs )

24 days ago

on Wednesday, March 19th 2025, 6:30:00 pm
89.06%
Financial Progress

11th Expenditure
of ₹ 15853 (0.16 Lacs ) done.
Cummulative ₹ 69.18Lacs ( against 77.68Lacs )

23 days ago

on Thursday, March 20th 2025, 6:30:00 pm
95.37%
Financial Progress

13th Expenditure
of ₹ 235826 (2.36 Lacs ) done.
Cummulative ₹ 74.08Lacs ( against 77.68Lacs )

23 days ago

on Thursday, March 20th 2025, 6:30:00 pm
92.33%
Financial Progress

12th Expenditure
of ₹ 253816 (2.54 Lacs ) done.
Cummulative ₹ 71.72Lacs ( against 77.68Lacs )

20 days ago

on Sunday, March 23rd 2025, 6:30:00 pm
98.57%
Financial Progress

14th Expenditure
of ₹ 249059 (2.49 Lacs ) done.
Cummulative ₹ 76.57Lacs ( against 77.68Lacs )