Work Sanctioned
जिला योजना वर्ष 2023-24 के अन्तर्गत रा0स्ना0महा0वि0, गोपेश्वर के लिंक मार्ग में दीवार, सी॰सी॰, रेलिंग आदि का कार्य
on Friday, June 9th 2023, 5:12:27 am
Technical Sanction
of ₹ 5.5 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1920/16 C
on Monday, December 4th 2023, 12:26:27 am
PWD UttarakahndPhoto (ID 31202) from Site Received
Uploader : Sachin Ashok, Assistant Engineer Civil ,CD Tharali
Landmark : PG college Gopeshwar
Remark : Laying of CC pavement
on Friday, January 12th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, February 27th 2024, 6:30:00 pm
36.37%
Financial Progress
1st Expenditure
of ₹ 200010 (2.00 Lacs ) done.
Cummulative ₹ 2.00Lacs ( against 5.5Lacs )
on Thursday, November 28th 2024, 6:30:00 pm
96.19%
Financial Progress
2nd Expenditure
of ₹ 329020 (3.29 Lacs ) done.
Cummulative ₹ 5.29Lacs ( against 5.5Lacs )