Bridge (ID- 1045 ) Inventory Report

Belki mashihi Bridge 50M

Data finalized On 20 Sep 2022

By Arvind Rawat

Last Rated On 03 Dec 2024

Rating 0.00%

Categorized As

XXXXX on XX-XX-XXXX

In District : Haridwar Under Division : PD Haridwar

General

Bridge Type : Motor Bridge High Level
Structure No : 2/3
Feature Intersected : Haljora Nala
Name of Bridge : Belki mashihi Bridge 50M
Nearest Town : Piranclear ,Roorkee
Latitude (Northing) : 30.00666667
Longitude (Easting) : 77.88083333
Construction Year : 2016
Inventory Year : 2021

Geometric

Overall length (in meter) : 50.00
Total No of Span : 2
Maximuam Span (in meter) : 25.00
Span Arragment : 2x25
No of Lane : 2.000
Overall Width (m) : 8.500
Carriageway Width (m) : 7.500
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 8.500
Gradient (%age) : 3
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.2
Design Loading : Class A
Load Rating : Class A

Super-Structure

Superstructure Type : T-beam and slab
Superstructure Material : Reinforced concrete
Wearing Coat Type : Cement Concrete
Expension Joint Type : Single Strip/Box Seal Joint
Railing/Crash Barrier type : Cast-in-situ concrete
Bearing type : Elastomeric

Sub-Structure

Founding Strata : Hard clayey
Abutment Foundation Type : Well
Pier Foundation Type : Well
No of Piers : 1
Abutment Type : RCC counterfort type
Pier Type : RCC Solid

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided