Bridge (ID- 107 ) Inventory Report

Bridge On Chainage 1.750 of Road from km 7 of Bungachhina Algda road to Kachna

Data finalized On 23 Dec 2022

By Pardeep Kumar AAE Civil

Last Rated On 22 Jun 2024

Rating 0.00%

Categorized As

XXXXX on XX-XX-XXXX

In District : Dehradun Under Division : TD Sahiya

General

Bridge Type : Motor Bridge High Level
Structure No : 2/1
Feature Intersected : local Gadera
Name of Bridge :
Nearest Town : Vyasi Poewr project
Latitude (Northing) : 30.54448000
Longitude (Easting) : 77.90569000
Construction Year : 2014
Inventory Year : 2014

Geometric

Overall length (in meter) : 9.60
Total No of Span : 1
Maximuam Span (in meter) : 9.00
Span Arragment : 1x9
No of Lane : 1.000
Overall Width (m) : 6.000
Carriageway Width (m) : 5.400
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 7.000
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre : 0.000
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Severe
Seismic Importance factor : 1.0
Design Loading : Class A
Load Rating : Class A

Super-Structure

Superstructure Type : Solid slab
Superstructure Material : Reinforced concrete
Wearing Coat Type : Not Provided
Expension Joint Type : Not Provided
Railing/Crash Barrier type : Cast-in-situ concrete
Bearing type : Not Provided

Sub-Structure

Founding Strata : Rocky
Abutment Foundation Type : Raft
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : Plum concrete block protection
Bank Protection Right Side of Up-stream : Plum concrete block protection
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : Plum concrete
Floor Protection on Down-stream : Plum concrete block protection
Tratment for Corrosion Protection (if any) : not required