Bridge (ID- 1142 ) Inventory Report

64 m Ganga nagar steel truss bridge On Chainage 0.030 of Vijaynagar Pathalidhar motor road

Data finalized On 22 Apr 2023

By Er. Parmanand Ram Devradi

Last Rated On 13 Jun 2024

Rating 0.09%

Categorized As

XXXXX on XX-XX-XXXX

In District : Rudraprayag Under Division : CD Ukhimath

General

Bridge Type : Motor Bridge High Level
Structure No : 1
Feature Intersected : Mandakini River
Name of Bridge : 64 m Ganga nagar steel truss bridge
Nearest Town : Agustmuni
Latitude (Northing) : 30.40022300
Longitude (Easting) : 79.04171300
Construction Year :
Inventory Year : 2010

Geometric

Overall length (in meter) : 64.00
Total No of Span : 1
Maximuam Span (in meter) : 64.00
Span Arragment : 1x64
No of Lane : 1.000
Overall Width (m) : 4.300
Carriageway Width (m) : 4.300
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 6.000
Gradient (%age) : 1
Skew Angle (degree) : 10.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.0
Design Loading : Class B
Load Rating : Class B

Super-Structure

Superstructure Type : Truss
Superstructure Material : Steel
Wearing Coat Type : Cement Concrete
Expension Joint Type : Single Strip/Box Seal Joint
Railing/Crash Barrier type : Tubular steel
Bearing type : POT PIN

Sub-Structure

Founding Strata : Rocky
Abutment Foundation Type : Open
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided