Bridge (ID- 1192 ) Inventory Report

Pedestrain Bridge at Km 10.050 in Bhujgad River On Chainage 10.050 of Road from Junior High School in village Nakulia to Raisikh Basti Towards North

Data finalized On 12 Dec 2022

By Yateesh Bisht

Last Rated On 16 May 2024

Rating 9.82%

Categorized As

XXXXX on XX-XX-XXXX

In District : Pithoragarh Under Division : PD Didihaat

General

Bridge Type : Pedestrain Bridge
Structure No : 11/1
Feature Intersected : Bhujgad
Name of Bridge : Pedestrain Bridge at Km 10.050 in Bhujgad River
Nearest Town : Dhanar
Latitude (Northing) : 29.96978900
Longitude (Easting) : 80.22415800
Construction Year :
Inventory Year : 2020

Geometric

Overall length (in meter) : 21.00
Total No of Span : 1
Maximuam Span (in meter) : 21.00
Span Arragment : 1x21
No of Lane : 1.000
Overall Width (m) : 2.000
Carriageway Width (m) : 1.800
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 2.000
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 0.0
Design Loading : Footpath Live Load
Load Rating : Footpath Live Load

Super-Structure

Superstructure Type : Truss
Superstructure Material : Steel
Wearing Coat Type : Cement Concrete
Expension Joint Type : Other
Railing/Crash Barrier type : Tubular steel
Bearing type : Not Provided

Sub-Structure

Founding Strata : Rocky
Abutment Foundation Type : Open
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided