Bridge (ID- 1259 ) Inventory Report

Pre stressed concrete Bridge On Chainage 7.800 of Manglor Nanuta Devband state highway

Data finalized On 19 Dec 2023

By Shivani Saini

Last Rated On 28 Nov 2024

Rating 0.89%

Categorized As

XXXXX on XX-XX-XXXX

In District : Haridwar Under Division : CD Roorkee

General

Bridge Type : Motor Bridge High Level
Structure No : 1/12
Feature Intersected : Sheela khala
Name of Bridge : Pre stressed concrete Bridge
Nearest Town : Narsan
Latitude (Northing) : 29.73328000
Longitude (Easting) : 77.80451000
Construction Year : 1987
Inventory Year : 2021

Geometric

Overall length (in meter) : 50.60
Total No of Span : 2
Maximuam Span (in meter) : 25.30
Span Arragment : 2x25.30
No of Lane : 1.000
Overall Width (m) : 8.100
Carriageway Width (m) : 8.100
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 11.000
Gradient (%age) : 0
Skew Angle (degree) : 30.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.0
Design Loading : Class A
Load Rating : Class A

Super-Structure

Superstructure Type : T-beam and slab
Superstructure Material : Reinforced concrete
Wearing Coat Type : Cement Concrete
Expension Joint Type : Not Provided
Railing/Crash Barrier type : Cast-in-situ concrete
Bearing type : other

Sub-Structure

Founding Strata : Soft clayey
Abutment Foundation Type : Well
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : RCC spill through type
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided