Bridge (ID- 1276 ) Inventory Report

RCC BOX Culvert On Chainage 2.700 of Puhana Jhabreda Iqbalpur Gurkul Narsan state highway

Data Yet Not Finalized

Last Rated On 26 May 2024

Rating 0.27%

Categorized As

XXXXX on XX-XX-XXXX

In District : Haridwar Under Division : CD Roorkee

General

Bridge Type : Motor Bridge High Level
Structure No : 6/19
Feature Intersected : Nala
Name of Bridge : RCC BOX Culvert
Nearest Town : puhana
Latitude (Northing) : 29.89468000
Longitude (Easting) : 77.82583000
Construction Year : 2015
Inventory Year : 2021

Geometric

Overall length (in meter) : 15.00
Total No of Span : 5
Maximuam Span (in meter) : 15.00
Span Arragment : 3x5
No of Lane : 2.000
Overall Width (m) : 10.000
Carriageway Width (m) : 10.000
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 12.000
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.0
Design Loading : Class A
Load Rating : Class A

Super-Structure

Superstructure Type : Box girder
Superstructure Material : Reinforced concrete
Wearing Coat Type : Bituminous Concrete
Expension Joint Type : Not Provided
Railing/Crash Barrier type : Cast-in-situ concrete
Bearing type : Not Provided

Sub-Structure

Founding Strata : Soft clayey
Abutment Foundation Type : Open
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : RCC Box type
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided