Bridge (ID- 141 ) Inventory Report

Ghattu Gaad Bridge

Data finalized On 03 Dec 2022

By PEEYUSH NEGI

Last Rated On 27 May 2024

Rating 3.48%

Categorized As

XXXXX on XX-XX-XXXX

In District : Uttarkashi Under Division : CD Uttarkashi

General

Bridge Type : Motor Bridge High Level
Structure No : 26/09
Feature Intersected : Ghattu Gaad
Name of Bridge : Ghattu Gaad Bridge
Nearest Town : Bhangwaal Gaon
Latitude (Northing) : 30.54472200
Longitude (Easting) : 78.41444400
Construction Year : 1970
Inventory Year : 2021

Geometric

Overall length (in meter) : 13.95
Total No of Span : 1
Maximuam Span (in meter) : 13.95
Span Arragment : 1x13.95
No of Lane : 1.000
Overall Width (m) : 4.600
Carriageway Width (m) : 4.000
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 5.600
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.0
Design Loading : Class A
Load Rating : Class A

Super-Structure

Superstructure Type : T-beam and slab
Superstructure Material : Reinforced concrete
Wearing Coat Type : Cement Concrete
Expension Joint Type : Single Strip/Box Seal Joint
Railing/Crash Barrier type : Tubular steel
Bearing type : Roller & Rocker

Sub-Structure

Founding Strata : Soft clayey
Abutment Foundation Type : Raft
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided