Bridge (ID- 1760 ) Inventory Report

Kalnoo On Chainage 26.100 of Dwarsoan Kakrighat motor road( From Dwarsoan)

Data finalized On 18 Nov 2022

By Er. Pradeep Joshi

Last Rated On 15 May 2024

Rating 0.00%

Categorized As

XXXXX on XX-XX-XXXX

In District : Almora Under Division : PD Almora

General

Bridge Type : Motor Bridge High Level
Structure No : 26/01
Feature Intersected : Kalnoo Gdhera
Name of Bridge : Kalnoo
Nearest Town : Ranikhet
Latitude (Northing) : 29.62059400
Longitude (Easting) : 79.50145600
Construction Year : 2014
Inventory Year : 2020

Geometric

Overall length (in meter) : 24.00
Total No of Span : 1
Maximuam Span (in meter) : 24.00
Span Arragment : 1×24.00
No of Lane : 1.000
Overall Width (m) : 4.750
Carriageway Width (m) : 4.250
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 6.000
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Mild
Seismic Importance factor : 0.0
Design Loading : NA
Load Rating : NA

Super-Structure

Superstructure Type : Solid slab
Superstructure Material : Steel
Wearing Coat Type : Cement Concrete
Expension Joint Type : Single Strip/Box Seal Joint
Railing/Crash Barrier type : Steel rolled section
Bearing type : Roller & Rocker

Sub-Structure

Founding Strata : Rocky
Abutment Foundation Type : Open
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided