Data finalized On 09 Aug 2022
By Er. Govind Singh Mahara
Last Rated On 28 Jun 2024
Rating 0.31%
Categorized As
XXXXX on XX-XX-XXXX
In District : Bageshwar Under Division : CD Kapkot
General
Bridge Type :
Pedestrain Bridge
Structure No :
1/1
Feature Intersected :
Local Gadhera
Name of Bridge :
30 Mtr Span Bridle Bridge at Seemabagar
Nearest Town :
Sumgarh
Latitude (Northing) :
30.02611944
Longitude (Easting) :
79.96396388
Construction Year :
2017
Inventory Year :
2020
Geometric
Overall length (in meter) :
30.00
Total No of Span :
1
Maximuam Span (in meter) :
30.00
Span Arragment :
1x30
No of Lane :
1.000
Overall Width (m) :
1.800
Carriageway Width (m) :
1.800
RS Footpath Width (m) :
0.000
LS Footpath Width (m) :
0.000
Approch Width i/c Shoulders (m) :
2.000
Gradient (%age) :
0
Skew Angle (degree) :
0.00
Radius of Curve in Plan (if Any) :
0.00
Design Data
HFL Highest Flood Level :
1701.000
OFL Ordinary Flood Level :
1700.300
LWL Low Water Level :
1700.000
Design Velocity (m/Sec) :
4.00
Design Discharge (Cumecs) :
55.00
Soffit Level at Centre :
1707.000
Road Level at Centre :
1708.000
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition :
Moderate
Seismic Importance factor :
0.0
Design Loading :
Footpath Live Load
Load Rating :
Footpath Live Load
Super-Structure
Superstructure Type :
Truss
Superstructure Material :
Steel
Wearing Coat Type :
Cement Concrete
Expension Joint Type :
Single Strip/Box Seal Joint
Railing/Crash Barrier type :
Steel rolled section
Bearing type :
POT PIN
Sub-Structure
Founding Strata :
Rocky
Abutment Foundation Type :
Raft
Pier Foundation Type :
NA
No of Piers :
0
Abutment Type :
Stone Masonry
Pier Type :
NA
Protection Work
Bank Protection Left Side of Up-stream :
Plume Concrete Block & Wirecrate
Bank Protection Right Side of Up-stream :
Plume Concrete Block
Bank Protection Left Side of Down-stream :
no protection work provided
Bank Protection Right Side of Down-stream :
no protection work provided
Floor Protection on Up-stream :
no protection work provided
Floor Protection on Down-stream :
no protection work provided
Tratment for Corrosion Protection (if any) :