Bridge (ID- 1868 ) Inventory Report

Bhisraw Bridge On Chainage 1.750 of Khunt-Dhamas-Basar-Jyoli Motor Road

Data finalized On 26 Dec 2022

By P. C. Pant

Last Rated On 27 May 2024

Rating 0.00%

Categorized As

XXXXX on XX-XX-XXXX

In District : Almora Under Division : PD Almora

General

Bridge Type : Motor Bridge High Level
Structure No : 2/3
Feature Intersected : Bhisraw Gadhera
Name of Bridge : Bhisraw Bridge
Nearest Town : Dhamus
Latitude (Northing) : 29.59654200
Longitude (Easting) : 79.57019100
Construction Year : 2018
Inventory Year : 2022

Geometric

Overall length (in meter) : 7.10
Total No of Span : 1
Maximuam Span (in meter) : 6.00
Span Arragment : 1x6
No of Lane : 1.000
Overall Width (m) : 6.000
Carriageway Width (m) : 5.450
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 7.500
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.0
Design Loading : Class A
Load Rating : NA

Super-Structure

Superstructure Type : Solid slab
Superstructure Material : Reinforced concrete
Wearing Coat Type : Cement Concrete
Expension Joint Type : Not Provided
Railing/Crash Barrier type : other
Bearing type : Not Provided

Sub-Structure

Founding Strata : Hard clayey
Abutment Foundation Type : Raft
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided