Bridge (ID- 1942 ) Inventory Report

Bridge at Kansali Gad On Chainage 32.908 of Lambgaon Motna Rajakhet Ghansali Sendul state highway

Data finalized On 05 Aug 2023

By Shri Anoop Rawat

Last Rated On 06 Jun 2024

Rating 0.00%

Categorized As

XXXXX on XX-XX-XXXX

In District : Tehri Under Division : PD New Tehri

General

Bridge Type : Motor Bridge High Level
Structure No : 32/36
Feature Intersected : Kansali Gad
Name of Bridge : Bridge at Kansali Gad
Nearest Town : Madan Negi
Latitude (Northing) : 30.42508400
Longitude (Easting) : 78.48204800
Construction Year : 2012
Inventory Year : 2022

Geometric

Overall length (in meter) : 18.80
Total No of Span : 1
Maximuam Span (in meter) : 18.80
Span Arragment : 1X18.80
No of Lane : 1.500
Overall Width (m) : 6.200
Carriageway Width (m) : 5.650
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 7.500
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre : 1140.000
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 0.0
Design Loading : Class B
Load Rating : Class B

Super-Structure

Superstructure Type : T-beam and slab
Superstructure Material : Reinforced concrete
Wearing Coat Type : Cement Concrete
Expension Joint Type : Single Strip/Box Seal Joint
Railing/Crash Barrier type : other
Bearing type : POT PIN

Sub-Structure

Founding Strata : Rocky
Abutment Foundation Type : Open
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided