Bridge (ID- 207 ) Inventory Report

DUNAO BRIDGE On Chainage 169.000 of Shaheed Sandeep Singh Rawat state highway (Ghattugad Silogi Gumkhal Lansdowne Deriyakhal Rikhanikhal Biroukhal motor road)

Data finalized On 14 Nov 2022

By VISHNU

Last Rated On 08 May 2024

Rating 1.13%

Categorized As

XXXXX on XX-XX-XXXX

In District : Pauri Under Division : PD Lansdown

General

Bridge Type : Motor Bridge High Level
Structure No : 169/1
Feature Intersected : EASTERN NAYAR
Name of Bridge : DUNAO BRIDGE
Nearest Town : DUNAO
Latitude (Northing) : 29.83126200
Longitude (Easting) : 78.97622000
Construction Year : 1993
Inventory Year : 2020

Geometric

Overall length (in meter) : 48.00
Total No of Span : 1
Maximuam Span (in meter) : 48.00
Span Arragment : 1X48
No of Lane : 1.000
Overall Width (m) : 4.270
Carriageway Width (m) : 3.750
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 6.000
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.0
Design Loading : Class B
Load Rating : Class B

Super-Structure

Superstructure Type : Truss
Superstructure Material : Steel
Wearing Coat Type : Bituminous Concrete
Expension Joint Type : Other
Railing/Crash Barrier type : Steel rolled section
Bearing type : Roller & Rocker

Sub-Structure

Founding Strata : Rocky
Abutment Foundation Type : Open
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided