Bridge (ID- 2081 ) Inventory Report

Irrigation mirror on NH 58 TO Ulheda m rd On Chainage 1.250 of Road from NH-58 Rajwahera towards Ulheda.

Data finalized On 05 Dec 2022

By Alka Rani/Yogesh Kumar

Last Rated On 25 May 2024

Rating 0.12%

Categorized As

XXXXX on XX-XX-XXXX

In District : Haridwar Under Division : CD Laksar

General

Bridge Type : Motor Bridge High Level
Structure No : 2/2
Feature Intersected : Minor
Name of Bridge : Irrigation mirror on NH 58 TO Ulheda m rd
Nearest Town : Narsan
Latitude (Northing) : 29.68200000
Longitude (Easting) : 77.83800000
Construction Year : 2010
Inventory Year : 2022

Geometric

Overall length (in meter) : 7.50
Total No of Span : 1
Maximuam Span (in meter) : 7.50
Span Arragment : 3x2.50
No of Lane : 1.000
Overall Width (m) : 7.600
Carriageway Width (m) : 6.900
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 8.000
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.0
Design Loading : Class A
Load Rating : Class A

Super-Structure

Superstructure Type : Solid slab
Superstructure Material : Reinforced concrete
Wearing Coat Type : Cement Concrete
Expension Joint Type : Not Provided
Railing/Crash Barrier type : other
Bearing type : Not Provided

Sub-Structure

Founding Strata : Sandy
Abutment Foundation Type : Open
Pier Foundation Type : Raft
No of Piers : 0
Abutment Type : Brick Masonry
Pier Type : RCC Solid

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided