Bridge (ID- 2086 ) Inventory Report

RCC Arch bridge On Chainage 3.000 of Bunga Sakhnikhet bhedgavn motor road

Data finalized On 26 Nov 2022

By Er. Sushil Semwal

Last Rated On 28 Nov 2024

Rating 0.00%

Categorized As

XXXXX on XX-XX-XXXX

In District : Pauri Under Division : PD Pauri

General

Bridge Type : Motor Bridge High Level
Structure No : 3/1
Feature Intersected : Kundi gadera
Name of Bridge : RCC Arch bridge
Nearest Town : Vill. Kund
Latitude (Northing) : 29.97319000
Longitude (Easting) : 78.70192000
Construction Year : 1980
Inventory Year : 2022

Geometric

Overall length (in meter) : 8.50
Total No of Span : 1
Maximuam Span (in meter) : 8.50
Span Arragment : 1*8.50
No of Lane : 1.000
Overall Width (m) : 6.500
Carriageway Width (m) : 5.900
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 7.600
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level : 694.000
OFL Ordinary Flood Level : 690.000
LWL Low Water Level : 688.000
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre : 698.000
Road Level at Centre : 699.000
Design Scour Level at Pier :
Design Scour Level at Abutments : 686.000
Exposure Condition : Moderate
Seismic Importance factor : 1.0
Design Loading : Class B
Load Rating : Class B

Super-Structure

Superstructure Type : Arch
Superstructure Material : Reinforced concrete
Wearing Coat Type : Bituminous Concrete
Expension Joint Type : Not Provided
Railing/Crash Barrier type : other
Bearing type : Not Provided

Sub-Structure

Founding Strata : Rocky
Abutment Foundation Type : Open
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided