Bridge (ID- 2202 ) Inventory Report

Hadvaha Nala Bridge On Chainage 28.600 of Purkazi Laksar Haridwar national highway

Data finalized On 19 Sep 2023

By Mahabir Lal AAE

Last Rated On 17 Nov 2023

Rating 0.57%

Categorized As

XXXXX on XX-XX-XXXX

In District : Haridwar Under Division : NH Dehradun

General

Bridge Type : Motor Bridge High Level
Structure No : 3/4
Feature Intersected : Hadvaha Nala
Name of Bridge : Hadvaha Nala Bridge
Nearest Town : Laksar
Latitude (Northing) : 29.73525000
Longitude (Easting) : 78.01142778
Construction Year : 1983
Inventory Year : 2022

Geometric

Overall length (in meter) : 36.00
Total No of Span : 4
Maximuam Span (in meter) : 9.00
Span Arragment : 4x9
No of Lane : 2.000
Overall Width (m) : 8.000
Carriageway Width (m) : 7.500
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 14.000
Gradient (%age) : 3
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level : 250.000
OFL Ordinary Flood Level : 150.000
LWL Low Water Level : 100.000
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.0
Design Loading : Class A
Load Rating : Class A

Super-Structure

Superstructure Type : T-beam and slab
Superstructure Material : Reinforced concrete
Wearing Coat Type : Cement Concrete
Expension Joint Type : Single Strip/Box Seal Joint
Railing/Crash Barrier type : Tubular steel
Bearing type : POT PIN

Sub-Structure

Founding Strata : Soft clayey
Abutment Foundation Type : Open
Pier Foundation Type : Well
No of Piers : 3
Abutment Type : RCC counterfort type
Pier Type : RCC Solid

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided