Bridge (ID- 2350 ) Inventory Report

GIC Lohaghat to Marorakhan Motor Bridge On Chainage 4.000 of Marorakhan-Raikot GIC Lohaghat M/R : Marorakhan-Raikot GIC Lohaghat M/R

Data finalized On 22 Nov 2022

By Navin Chandra

Last Rated On 15 Oct 2024

Rating 0.00%

Categorized As

XXXXX on XX-XX-XXXX

In District : Champawat Under Division : CD Lohaghat

General

Bridge Type : Motor Bridge High Level
Structure No : 1/1
Feature Intersected : batel
Name of Bridge : GIC Lohaghat to Marorakhan Motor Bridge
Nearest Town : Lohaghat
Latitude (Northing) : 29.41241800
Longitude (Easting) : 80.09443400
Construction Year : 2010
Inventory Year : 2022

Geometric

Overall length (in meter) : 6.00
Total No of Span : 1
Maximuam Span (in meter) : 6.00
Span Arragment : 1x6
No of Lane : 1.000
Overall Width (m) : 5.500
Carriageway Width (m) : 4.800
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 5.950
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.0
Design Loading : Class B
Load Rating : Class B

Super-Structure

Superstructure Type : Solid slab
Superstructure Material : Reinforced concrete
Wearing Coat Type : Cement Concrete
Expension Joint Type : Not Provided
Railing/Crash Barrier type : Tubular steel
Bearing type : Not Provided

Sub-Structure

Founding Strata : Rocky
Abutment Foundation Type : Raft
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided