Bridge (ID- 2352 ) Inventory Report

Bhamki Gaarh On Chainage 2.825 of Naghar Kumlta motor road (VR)

Data finalized On 19 Jul 2025

By Mukesh chandra Jukaria

Last Rated On 07 May 2026

Rating 0.00%

Categorized As

XXXXX on XX-XX-XXXX

In District : Pithoragarh Under Division : PD Pithoragarh

General

Bridge Type : Motor Bridge High Level
Structure No : 55
Feature Intersected : Bhamki Gaarh
Name of Bridge : Bhamki Gaarh
Nearest Town : Pithoragarh
Latitude (Northing) : 29.63033000
Longitude (Easting) : 80.24849000
Construction Year : 2015
Inventory Year : 2022
Work Code(s) : --

Geometric

Overall length (in meter) : 11.50
Total No of Span : 1
Maximuam Span (in meter) : 11.50
Span Arragment : 1 x 11.5
No of Lane : 1.000
Overall Width (m) : 5.000
Carriageway Width (m) : 4.500
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 6.000
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.5
Design Loading : Class B
Load Rating : Class B

Super-Structure

Superstructure Type : T-beam and slab
Superstructure Material : Reinforced concrete
Wearing Coat Type : Cement Concrete
Expension Joint Type : Not Provided
Railing/Crash Barrier type : Tubular steel
Bearing type : Not Provided

Sub-Structure

Founding Strata : Rocky
Abutment Foundation Type : Open
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided