Bridge (ID- 2570 ) Inventory Report

Chullikhet pull On Chainage 0.200 of Kodar deengaon Mukhem motor road

Data finalized On 05 Jan 2024

By Er. Brijesh Anthwal

Last Rated On 05 Jan 2024

Rating 1.21%

Categorized As

XXXXX on XX-XX-XXXX

In District : Tehri Under Division : PD New Tehri

General

Bridge Type : Motor Bridge High Level
Structure No : 1/8
Feature Intersected : local gadhera
Name of Bridge : Chullikhet pull
Nearest Town : Kodar
Latitude (Northing) : 30.58311389
Longitude (Easting) : 78.50002778
Construction Year : 2003
Inventory Year : 2020

Geometric

Overall length (in meter) : 9.00
Total No of Span : 1
Maximuam Span (in meter) : 9.00
Span Arragment : 1x9m
No of Lane : 1.000
Overall Width (m) : 5.000
Carriageway Width (m) : 4.250
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 5.000
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level : 1410.000
OFL Ordinary Flood Level : 1408.000
LWL Low Water Level : 1408.000
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre : 1412.000
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.0
Design Loading : Class B
Load Rating : Class B

Super-Structure

Superstructure Type : T-beam and slab
Superstructure Material : Reinforced concrete
Wearing Coat Type : Cement Concrete
Expension Joint Type : Single Strip/Box Seal Joint
Railing/Crash Barrier type : Tubular steel
Bearing type : other

Sub-Structure

Founding Strata : Rocky
Abutment Foundation Type : Open
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : plum protection
Bank Protection Right Side of Up-stream : plum protection
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided