Bridge (ID- 2655 ) Inventory Report

16 M Box Culvert at Badiwala On Chainage 0.870 of Buggawala Primary school to Badiwala road

Data finalized On 28 Dec 2022

By Arvind Rawat

Last Rated On 03 Dec 2024

Rating 0.00%

Categorized As

XXXXX on XX-XX-XXXX

In District : Haridwar Under Division : PD Haridwar

General

Bridge Type : Motor Bridge High Level
Structure No : 1/1
Feature Intersected : Barsati Nala
Name of Bridge : 16 M Box Culvert at Badiwala
Nearest Town : Badiwala
Latitude (Northing) : 30.08995556
Longitude (Easting) : 77.90998333
Construction Year : 2022
Inventory Year : 2022

Geometric

Overall length (in meter) : 16.00
Total No of Span : 4
Maximuam Span (in meter) : 16.00
Span Arragment : 4x4
No of Lane : 1.500
Overall Width (m) : 7.500
Carriageway Width (m) : 7.500
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 7.500
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.0
Design Loading : Class A
Load Rating : Class A

Super-Structure

Superstructure Type : Single/Multi-cell Box
Superstructure Material : Reinforced concrete
Wearing Coat Type : Cement Concrete
Expension Joint Type : Single Strip/Box Seal Joint
Railing/Crash Barrier type : Cast-in-situ concrete
Bearing type : Not Provided

Sub-Structure

Founding Strata : Bouldery
Abutment Foundation Type : Raft
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : RCC Box type
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided