Bridge (ID- 2899 ) Inventory Report

Doni Bridge

Data finalized On 06 Jan 2024

By Rajat Negi

Last Rated On 15 Jun 2024

Rating 0.16%

Categorized As

XXXXX on XX-XX-XXXX

In District : Rudraprayag Under Division : PD Rudraprayag

General

Bridge Type : Pedestrain Bridge
Structure No : 1/1
Feature Intersected : Doni Gadera
Name of Bridge : Doni Bridge
Nearest Town : Bainji Kandai
Latitude (Northing) : 30.33926900
Longitude (Easting) : 79.10822800
Construction Year : 2014
Inventory Year : 2022

Geometric

Overall length (in meter) : 15.00
Total No of Span : 1
Maximuam Span (in meter) : 15.00
Span Arragment : 1x15
No of Lane : 1.000
Overall Width (m) : 1.800
Carriageway Width (m) : 1.800
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 1.800
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 0.0
Design Loading : Footpath Live Load
Load Rating : Footpath Live Load

Super-Structure

Superstructure Type : T-beam and slab
Superstructure Material : Reinforced concrete
Wearing Coat Type : Cement Concrete
Expension Joint Type : Not Provided
Railing/Crash Barrier type : Tubular steel
Bearing type : Not Provided

Sub-Structure

Founding Strata : Bouldery
Abutment Foundation Type : Open
Pier Foundation Type : Open
No of Piers : 2
Abutment Type : Stone Masonry
Pier Type : Stone Masonry

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided