Bridge (ID- 2916 ) Inventory Report

Gaurikund Nala Bridge. On Chainage 4.550 of Sonprayag Gaurikund road

Data finalized On 12 Apr 2023

By Prasoon Nautiyal

Last Rated On 06 Dec 2023

Rating 0.51%

Categorized As

XXXXX on XX-XX-XXXX

In District : Rudraprayag Under Division : CD Guptkashi

General

Bridge Type : Pedestrain Bridge
Structure No : 5
Feature Intersected : Gaurikund Nala.
Name of Bridge : Gaurikund Nala Bridge.
Nearest Town : Gaurikund
Latitude (Northing) : 30.65130000
Longitude (Easting) : 79.46660000
Construction Year :
Inventory Year : 2020

Geometric

Overall length (in meter) : 9.00
Total No of Span : 1
Maximuam Span (in meter) : 9.00
Span Arragment : 3x3
No of Lane : 1.000
Overall Width (m) : 2.000
Carriageway Width (m) : 1.800
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 2.000
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.2
Design Loading : NA
Load Rating : NA

Super-Structure

Superstructure Type : Bailey
Superstructure Material : Steel
Wearing Coat Type : Not Provided
Expension Joint Type : Not Provided
Railing/Crash Barrier type : Steel rolled section
Bearing type : Not Provided

Sub-Structure

Founding Strata : Rocky
Abutment Foundation Type : Open
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : protection work provided
Bank Protection Right Side of Up-stream : protection work provided
Bank Protection Left Side of Down-stream : protection work provided
Bank Protection Right Side of Down-stream : protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided