Bridge (ID- 3005 ) Inventory Report

RCC Bridge in Chula-Gabani Motor Road in km-3

Data finalized On 09 Jan 2024

By Gautam Singh

Last Rated On 28 Nov 2024

Rating 0.31%

Categorized As

XXXXX on XX-XX-XXXX

In District : Chamoli Under Division : PD Karnprayag

General

Bridge Type : Motor Bridge High Level
Structure No : 3/2
Feature Intersected : Bagoli Gaad
Name of Bridge : RCC Bridge in Chula-Gabani Motor Road in km-3
Nearest Town : Bagoli Bazar
Latitude (Northing) : 30.18156100
Longitude (Easting) : 79.29641900
Construction Year : 2014
Inventory Year : 2022

Geometric

Overall length (in meter) : 12.00
Total No of Span : 1
Maximuam Span (in meter) : 12.00
Span Arragment : 1x12
No of Lane : 1.000
Overall Width (m) : 6.100
Carriageway Width (m) : 5.000
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 6.550
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 0.0
Design Loading : Class B
Load Rating : Class B

Super-Structure

Superstructure Type : T-beam and slab
Superstructure Material : Reinforced concrete
Wearing Coat Type : Cement Concrete
Expension Joint Type : Modular Strip/Box Seal Joints
Railing/Crash Barrier type : Tubular steel
Bearing type : Elastomeric

Sub-Structure

Founding Strata : Bouldery
Abutment Foundation Type : Open
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided