Bridge (ID- 3081 ) Inventory Report

BANGHAT-SHEELA VALLY BRIDGE On Chainage 4.000 of Banghat Silla Barali Kund Patli Naini Sildi Baneli Kenyur Thangar motor road

Data finalized On 27 Sep 2023

By RAHUL GUPTA

Last Rated On 01 Jun 2024

Rating 14.12%

Categorized As

XXXXX on XX-XX-XXXX

In District : Pauri Under Division : PD Lansdown

General

Bridge Type : Motor Bridge High Level
Structure No : 4/1
Feature Intersected : LOCAL RIVER
Name of Bridge : BANGHAT-SHEELA VALLY BRIDGE
Nearest Town : BANGHAT
Latitude (Northing) : 29.94883100
Longitude (Easting) : 78.67236300
Construction Year : 2021
Inventory Year : 2023

Geometric

Overall length (in meter) : 24.00
Total No of Span : 1
Maximuam Span (in meter) : 24.00
Span Arragment : 1X24
No of Lane : 1.000
Overall Width (m) : 4.270
Carriageway Width (m) : 3.750
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 5.950
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.0
Design Loading : Class B
Load Rating : Class B

Super-Structure

Superstructure Type : Bailey
Superstructure Material : Steel
Wearing Coat Type : Other
Expension Joint Type : Other
Railing/Crash Barrier type : Steel rolled section
Bearing type : Elastomeric

Sub-Structure

Founding Strata : Rocky
Abutment Foundation Type : Open
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided