Bridge (ID- 3088 ) Inventory Report

Steel bridge near fatehpur km 2 FL Road On Chainage 1.350 of Fathehpur Deriyakhal Lansdowne motor road.

Data finalized On 27 Sep 2023

By Mukesh kumar

Last Rated On 31 May 2024

Rating 0.00%

Categorized As

XXXXX on XX-XX-XXXX

In District : Pauri Under Division : PD Lansdown

General

Bridge Type : Motor Bridge High Level
Structure No : 2/1
Feature Intersected : dhobighat nala
Name of Bridge : Steel bridge near fatehpur km 2 FL Road
Nearest Town : fatehpur
Latitude (Northing) : 29.81950520
Longitude (Easting) : 78.62698040
Construction Year : 1985
Inventory Year : 2023

Geometric

Overall length (in meter) : 10.00
Total No of Span : 1
Maximuam Span (in meter) : 10.00
Span Arragment : 1x10
No of Lane : 1.000
Overall Width (m) : 4.500
Carriageway Width (m) : 4.000
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 5.950
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.0
Design Loading : Class B
Load Rating : Class B

Super-Structure

Superstructure Type : Plate Girder
Superstructure Material : Reinforced concrete
Wearing Coat Type : Bituminous Concrete
Expension Joint Type : Not Provided
Railing/Crash Barrier type : Steel rolled section
Bearing type : Not Provided

Sub-Structure

Founding Strata : Rocky
Abutment Foundation Type : Open
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided