Bridge (ID- 3257 ) Inventory Report

Pedestrial bridge in Harsadi over Ramganga River

Data finalized On 04 Jan 2024

By Praveen Bhandari

Last Rated On 24 May 2024

Rating 1.63%

Categorized As

XXXXX on XX-XX-XXXX

In District : Chamoli Under Division : CD Gairsain

General

Bridge Type : Pedestrain Bridge
Structure No : 189
Feature Intersected : Ramganga river
Name of Bridge : Pedestrial bridge in Harsadi over Ramganga River
Nearest Town : Harsari Gaou
Latitude (Northing) : 31.58416700
Longitude (Easting) : 79.75527800
Construction Year : 2005
Inventory Year : 2023

Geometric

Overall length (in meter) : 40.00
Total No of Span : 1
Maximuam Span (in meter) : 40.00
Span Arragment : 1X40
No of Lane : 1.000
Overall Width (m) : 1.800
Carriageway Width (m) : 2.400
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 2.400
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.0
Design Loading : Footpath Live Load
Load Rating : Footpath Live Load

Super-Structure

Superstructure Type : T-beam and slab
Superstructure Material : Steel
Wearing Coat Type : Other
Expension Joint Type : Single Strip/Box Seal Joint
Railing/Crash Barrier type : Tubular steel
Bearing type : Elastomeric

Sub-Structure

Founding Strata : Rocky
Abutment Foundation Type : Raft
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided