Bridge (ID- 333 ) Inventory Report

Dhela On Chainage 0.650 of Dhela bridge to Manpur Firojpur stadium via Nagnath temple road

Data finalized On 14 Jan 2022

By Chetan Bhatt

Last Rated On 31 May 2024

Rating 1.56%

Categorized As

XXXXX on XX-XX-XXXX

In District : Udham Singh Nagar Under Division : CD Kashipur

General

Bridge Type : Motor Bridge High Level
Structure No : 1/1
Feature Intersected : Dhela river
Name of Bridge : Dhela
Nearest Town : Kashipur
Latitude (Northing) : 29.22027700
Longitude (Easting) : 78.94472200
Construction Year : 2011
Inventory Year : 2020

Geometric

Overall length (in meter) : 180.00
Total No of Span : 6
Maximuam Span (in meter) : 30.00
Span Arragment : 6*30
No of Lane : 2.000
Overall Width (m) : 11.500
Carriageway Width (m) : 7.500
RS Footpath Width (m) : 1.000
LS Footpath Width (m) : 1.000
Approch Width i/c Shoulders (m) : 9.500
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level : 219.700
OFL Ordinary Flood Level :
LWL Low Water Level : 215.800
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.0
Design Loading : Class AA
Load Rating : Class A

Super-Structure

Superstructure Type : T-beam and slab
Superstructure Material : Reinforced concrete
Wearing Coat Type : Cement Concrete
Expension Joint Type : Single Strip/Box Seal Joint
Railing/Crash Barrier type : Tubular steel
Bearing type : Elastomeric

Sub-Structure

Founding Strata : Sandy
Abutment Foundation Type : Well
Pier Foundation Type : Well
No of Piers : 5
Abutment Type : Stone Masonry
Pier Type : RCC Solid

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided