Bridge (ID- 3483 ) Inventory Report

अकौढा खुर्द में पथरी रोह सेतु (बाॅक्स सेल) On Chainage 1.600 of Akoda Khurd to Ban Ganga river motor road.

Data finalized On 05 Oct 2024

By ER. Dinesh Kumar

Last Rated On 12 Sep 2024

Rating 0.00%

Categorized As

XXXXX on XX-XX-XXXX

In District : Haridwar Under Division : CD Laksar

General

Bridge Type : Motor Bridge High Level
Structure No : 2/1
Feature Intersected : पथरी रोह सेतु
Name of Bridge : अकौढा खुर्द में पथरी रोह सेतु (बाॅक्स सेल)
Nearest Town : Akodha Khurd
Latitude (Northing) : 29.70434800
Longitude (Easting) : 78.06719500
Construction Year : 2022
Inventory Year : 2022

Geometric

Overall length (in meter) : 50.00
Total No of Span : 9
Maximuam Span (in meter) : 50.00
Span Arragment : 5x9m
No of Lane : 2.000
Overall Width (m) : 8.400
Carriageway Width (m) : 7.500
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 8.400
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Mild
Seismic Importance factor : 1.0
Design Loading : Class A
Load Rating : Class A

Super-Structure

Superstructure Type : T-beam and slab
Superstructure Material : Reinforced concrete
Wearing Coat Type : Cement Concrete
Expension Joint Type : Single Strip/Box Seal Joint
Railing/Crash Barrier type : Tubular steel
Bearing type : POT PIN

Sub-Structure

Founding Strata : Sandy
Abutment Foundation Type : Raft
Pier Foundation Type : Raft
No of Piers : 11
Abutment Type : RCC Box type
Pier Type : RCC Solid

Protection Work

Bank Protection Left Side of Up-stream : Bolder Pitching, Pullam Concrete
Bank Protection Right Side of Up-stream : Bolder Pitching, Pullam Concrete
Bank Protection Left Side of Down-stream : Bolder Pitching, Pullam Concrete
Bank Protection Right Side of Down-stream : Bolder Pitching, Pullam Concrete
Floor Protection on Up-stream : Cut of Wall, Curtain Wall
Floor Protection on Down-stream : Cut of Wall, Curtain Wall
Tratment for Corrosion Protection (if any) : no special treatment provided