Bridge (ID- 3803 ) Inventory Report

khitoli bridge On Chainage 4.230 of Tanakpur Pithoragrh motor road to Gogina village motor road (LVR)

Data finalized On 01 Jun 2026

By Beena Pande

Last Rated On 29 Oct 2026

Rating 0.99%

Categorized As

XXXXX on XX-XX-XXXX

In District : Pithoragarh Under Division : PD Pithoragarh

General

Bridge Type : Motor Bridge High Level
Structure No : 5/1
Feature Intersected : khitoli milan gaad
Name of Bridge : khitoli bridge
Nearest Town : Pithoragarh
Latitude (Northing) : 29.50537700
Longitude (Easting) : 80.15505100
Construction Year : 2012
Inventory Year : 2013
Work Code(s) : --

Geometric

Overall length (in meter) : 9.00
Total No of Span : 1
Maximuam Span (in meter) : 9.00
Span Arragment : 1x9.00
No of Lane : 1.000
Overall Width (m) : 4.650
Carriageway Width (m) : 4.250
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 5.950
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.0
Design Loading : Class B
Load Rating : Class B

Super-Structure

Superstructure Type : T-beam and slab
Superstructure Material : Reinforced concrete
Wearing Coat Type : Cement Concrete
Expension Joint Type : Not Provided
Railing/Crash Barrier type : Not Provided
Bearing type : Not Provided

Sub-Structure

Founding Strata : Rocky
Abutment Foundation Type : other
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided