Bridge (ID- 3899 ) Inventory Report

Bridge near Kharsari at TPN km 40 On Chainage 40.000 of Tuni Purola Naugaon state highway (SH)

Data finalized On 19 Sep 2026

By kailash Rana

Bridge Yet Not Rated

Categorized As

XXXXX on XX-XX-XXXX

In District : Uttarkashi Under Division : CD Purola

General

Bridge Type : Motor Bridge High Level
Structure No : 40/1
Feature Intersected : Local Khadd
Name of Bridge : Bridge near Kharsari at TPN km 40
Nearest Town : Mori
Latitude (Northing) : 30.96853300
Longitude (Easting) : 78.07412500
Construction Year : 1980
Inventory Year : 2026
Work Code(s) : --

Geometric

Overall length (in meter) : 12.70
Total No of Span : 1
Maximuam Span (in meter) : 12.70
Span Arragment : 1*12.70
No of Lane : 1.000
Overall Width (m) : 4.000
Carriageway Width (m) : 4.000
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 4.300
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level : 2500.000
OFL Ordinary Flood Level : 2300.000
LWL Low Water Level : 2000.000
Design Velocity (m/Sec) : 0.00
Design Discharge (Cumecs) : 0.00
Soffit Level at Centre : 0.000
Road Level at Centre : 0.000
Design Scour Level at Pier : 0.000
Design Scour Level at Abutments : 0.000
Exposure Condition : Moderate
Seismic Importance factor : 1.0
Design Loading : Class B
Load Rating : Class B

Super-Structure

Superstructure Type : T-beam and slab
Superstructure Material : Reinforced concrete
Wearing Coat Type : Cement Concrete
Expension Joint Type : Single Strip/Box Seal Joint
Railing/Crash Barrier type : Tubular steel
Bearing type : other

Sub-Structure

Founding Strata : Rocky
Abutment Foundation Type : Open
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided