Bridge (ID- 425 ) Inventory Report

Jantanwala bridge On Chainage 1.000 of Jantanwala to Dhaulas Road

Data finalized On 12 Jun 2024

By VINEET SAINI

Last Rated On 12 Jun 2024

Rating 0.00%

Categorized As

XXXXX on XX-XX-XXXX

In District : Dehradun Under Division : PD Dehradun

General

Bridge Type : Motor Bridge High Level
Structure No : 7
Feature Intersected : noon river
Name of Bridge : Jantanwala bridge
Nearest Town : Jantanwala
Latitude (Northing) : 30.22400000
Longitude (Easting) : 78.00520000
Construction Year : 2008
Inventory Year : 2020

Geometric

Overall length (in meter) : 156.00
Total No of Span : 7
Maximuam Span (in meter) : 150.00
Span Arragment : 21.5*7
No of Lane : 2.000
Overall Width (m) : 10.500
Carriageway Width (m) : 7.500
RS Footpath Width (m) : 1.500
LS Footpath Width (m) : 1.500
Approch Width i/c Shoulders (m) : 9.000
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.0
Design Loading : Class A
Load Rating : Class A

Super-Structure

Superstructure Type : T-beam and slab
Superstructure Material : Reinforced concrete
Wearing Coat Type : Cement Concrete
Expension Joint Type : Single Strip/Box Seal Joint
Railing/Crash Barrier type : Cast-in-situ concrete
Bearing type : other

Sub-Structure

Founding Strata : Bouldery
Abutment Foundation Type : Raft
Pier Foundation Type : Raft
No of Piers : 6
Abutment Type : other
Pier Type : RCC Solid

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided