Bridge (ID- 846 ) Inventory Report

Forms are not avilable

Steel girder bridle bridge at binwalgoun GIC over binwalgoun gadhera

Data finalized On 07 Dec 2023

By Pramod Kharakwal

Last Rated On 19 Jun 2025

Rating 2.27%

Categorized As

XXXXX on XX-XX-XXXX

In District : Champawat Under Division : PD Champawat

General

Bridge Type : Pedestrain Bridge
Structure No : 1/1
Feature Intersected : Binwalgoun gadhera
Name of Bridge : Steel girder bridle bridge at binwalgoun GIC over binwalgoun gadhera
Nearest Town : Reetha, Binwalgoun
Latitude (Northing) : 29.30272400
Longitude (Easting) : 79.84902800
Construction Year : 2005
Inventory Year : 2021

Geometric

Overall length (in meter) : 24.00
Total No of Span : 1
Maximuam Span (in meter) : 24.00
Span Arragment : 1x24
No of Lane : 1.000
Overall Width (m) : 1.800
Carriageway Width (m) : 1.800
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 1.800
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.0
Design Loading : Footpath Live Load
Load Rating : Footpath Live Load

Super-Structure

Superstructure Type : Truss
Superstructure Material : Steel
Wearing Coat Type : Not Provided
Expension Joint Type : Not Provided
Railing/Crash Barrier type : Steel rolled section
Bearing type : Elastomeric

Sub-Structure

Founding Strata : Rocky
Abutment Foundation Type : Open
Pier Foundation Type : NA
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided