Bridge (ID- 885 ) Inventory Report

Chandrabhaga river On Chainage 0.000 of Narendranagar-Suman Hospital-Military Gate-Door Motor Road.

Data Yet Not Finalized

Last Rated On 13 Nov 2023

Rating 12.11%

Categorized As

XXXXX on XX-XX-XXXX

In District : Tehri Under Division : CD Narendnagar

General

Bridge Type : Pedestrain Bridge
Structure No : 7/1
Feature Intersected : Chandrabhaga river
Name of Bridge : Chandrabhaga river
Nearest Town : Dour Village
Latitude (Northing) : 30.10366200
Longitude (Easting) : 78.16349400
Construction Year : 1973
Inventory Year : 2021

Geometric

Overall length (in meter) : 93.00
Total No of Span : 1
Maximuam Span (in meter) : 93.00
Span Arragment : 1x93
No of Lane : 1.000
Overall Width (m) : 2.500
Carriageway Width (m) : 2.000
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 3.500
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.0
Design Loading : Footpath Live Load
Load Rating : Footpath Live Load

Super-Structure

Superstructure Type : Suspension
Superstructure Material : Composite
Wearing Coat Type : Cement Concrete
Expension Joint Type : Compression Seal Joint
Railing/Crash Barrier type : Steel rolled section
Bearing type : Elastomeric

Sub-Structure

Founding Strata : Rocky
Abutment Foundation Type : Open
Pier Foundation Type : Open
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided