Bridge (ID- 888 ) Inventory Report

Over Local Gadhera Taminagar On Chainage 15.785 of Bikhyasain Deghat Bungidhar Mehalchori Bachuwaban Chokhutiya state highway

Data Yet Not Finalized

Last Rated On 16 May 2024

Rating 0.62%

Categorized As

XXXXX on XX-XX-XXXX

In District : Almora Under Division : PD Ranikhet

General

Bridge Type : Motor Bridge High Level
Structure No : 15/06
Feature Intersected : Over Local Gadhera Taminger
Name of Bridge : Over Local Gadhera Taminagar
Nearest Town : Syaldey
Latitude (Northing) : 29.83665700
Longitude (Easting) : 79.19411000
Construction Year : 1978
Inventory Year : 2020

Geometric

Overall length (in meter) : 7.50
Total No of Span : 1
Maximuam Span (in meter) : 6.00
Span Arragment : 1x7.50
No of Lane : 1.000
Overall Width (m) : 5.500
Carriageway Width (m) : 4.270
RS Footpath Width (m) : 0.000
LS Footpath Width (m) : 0.000
Approch Width i/c Shoulders (m) : 7.000
Gradient (%age) : 0
Skew Angle (degree) : 0.00
Radius of Curve in Plan (if Any) : 0.00

Design Data

HFL Highest Flood Level :
OFL Ordinary Flood Level :
LWL Low Water Level :
Design Velocity (m/Sec) :
Design Discharge (Cumecs) :
Soffit Level at Centre :
Road Level at Centre :
Design Scour Level at Pier :
Design Scour Level at Abutments :
Exposure Condition : Moderate
Seismic Importance factor : 1.5
Design Loading : Class B
Load Rating : Class SV

Super-Structure

Superstructure Type : Solid slab
Superstructure Material : Reinforced concrete
Wearing Coat Type : Cement Concrete
Expension Joint Type : Not Provided
Railing/Crash Barrier type : Pre-cast concrete
Bearing type : other

Sub-Structure

Founding Strata : Rocky
Abutment Foundation Type : Open
Pier Foundation Type : other
No of Piers : 0
Abutment Type : Stone Masonry
Pier Type : NA

Protection Work

Bank Protection Left Side of Up-stream : no protection work provided
Bank Protection Right Side of Up-stream : no protection work provided
Bank Protection Left Side of Down-stream : no protection work provided
Bank Protection Right Side of Down-stream : no protection work provided
Floor Protection on Up-stream : no protection work provided
Floor Protection on Down-stream : no protection work provided
Tratment for Corrosion Protection (if any) : no special treatment provided