All Features Report For CD Paboo
Road Segment Feature Chainage Length Cordinates Status Priority Install Date Repair Date Repair events Remark Updated On
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 149.000 - 149.088 88.000 29.9141360000, 78.9270810000 Estimation Done 8 Installed under road safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 149.400 - 149.432 32.000 29.9115660000, 78.9258340000 Estimation Done 7 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 149.600 - 149.624 24.000 29.9098150000, 78.9237530000 Estimation Done 8 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 149.700 - 149.744 44.000 29.9095520000, 78.9237230000 Estimation Done 8 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 149.800 - 149.832 32.000 29.9077510000, 78.9211940000 Estimation Done 8 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 150.000 - 150.028 28.000 29.9133790000, 78.9265650000 Estimation Done 0 Installed under road safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 150.150 - 150.174 24.000 29.9122070000, 78.9261860000 Estimation Done 8 Installed under road safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 150.210 - 150.266 56.000 29.9074790000, 78.9230540000 Estimation Done 8 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 150.400 - 150.440 40.000 29.9071140000, 78.9234610000 Estimation Done 7 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 151.600 - 151.628 28.000 29.9068750000, 78.9217690000 Estimation Done 8 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 151.800 - 151.808 8.000 29.9030230000, 78.9141920000 Estimation Done 8 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 151.850 - 151.898 48.000 29.9030360000, 78.9140310000 Estimation Done 8 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 152.140 - 152.192 52.000 29.9012550000, 78.9104560000 Estimation Done 7 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 152.200 - 152.236 36.000 29.9006740000, 78.9072150000 Estimation Done 8 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 152.400 - 152.412 12.000 29.9001900000, 78.9055580000 Estimation Done 7 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 152.430 - 152.486 56.000 29.9000370000, 78.9054220000 Estimation Done 8 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 152.600 - 152.624 24.000 29.8999860000, 78.9081500000 Estimation Done 8 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 152.630 - 152.694 64.000 29.8997490000, 78.9062040000 Estimation Done 7 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 152.700 - 152.772 72.000 29.8997760000, 78.9068920000 Estimation Done 7 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 152.800 - 152.844 44.000 29.8997480000, 78.9098250000 Estimation Done 7 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 153.080 - 153.128 48.000 29.8996170000, 78.9104040000 Estimation Done 7 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 153.150 - 153.194 44.000 29.8994190000, 78.9110970000 Estimation Done 7 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 153.200 - 153.236 36.000 29.8994840000, 78.9129860000 Estimation Done 8 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 154.690 - 154.718 28.000 29.8974820000, 78.9070380000 Estimation Done 7 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 154.750 - 154.778 28.000 29.8976920000, 78.9066670000 Estimation Done 7 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 154.960 - 154.996 36.000 29.8978900000, 78.9049320000 Estimation Done 10 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 162.600 - 162.648 48.000 29.8990630000, 78.8601060000 Estimation Done 7 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 162.750 - 162.770 20.000 29.8981890000, 78.8581820000 Estimation Done 7 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 162.820 - 162.848 28.000 29.8978890000, 78.8577260000 Estimation Done 8 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 163.850 - 163.926 76.000 29.9005850000, 78.8492310000 Estimation Done 6 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 169.550 - 169.614 64.000 29.9013770000, 78.8193450000 Estimation Done 8 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 169.580 - 169.588 8.000 29.9009520000, 78.8189630000 Estimation Done 8 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 169.700 - 169.712 12.000 29.0094600000, 78.8178860000 Estimation Done 8 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 169.900 - 169.952 52.000 29.0000000000, 78.0000000000 Estimation Done 8 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 170.050 - 170.094 44.000 29.9040450000, 78.8167590000 Estimation Done 8 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 170.200 - 170.256 56.000 29.9056770000, 78.8154800000 Estimation Done 7 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 170.600 - 170.632 32.000 29.9063630000, 78.8144250000 Estimation Done 7 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 170.700 - 170.776 76.000 29.9064470000, 78.8142890000 Estimation Done 9 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 170.800 - 170.848 48.000 29.9086340000, 78.8111320000 Estimation Done 9 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 171.020 - 171.096 76.000 29.9090570000, 78.8100670000 Estimation Done 7 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 171.100 - 171.124 24.000 29.9096610000, 78.8101370000 Estimation Done 7 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 171.600 - 171.684 84.000 29.9143040000, 78.8077460000 Estimation Done 8 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 171.800 - 171.832 32.000 29.9158450000, 78.8075310000 Estimation Done 7 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 172.010 - 172.118 108.000 29.9153800000, 78.8069050000 Estimation Done 7 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 172.600 - 172.624 24.000 29.9111920000, 78.8044660000 Estimation Done 8 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 172.700 - 172.736 36.000 29.9106940000, 78.8042180000 Estimation Done 8 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 172.800 - 172.856 56.000 29.9106660000, 78.8038580000 Estimation Done 8 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 173.020 - 173.068 48.000 29.9098780000, 78.8023200000 Estimation Done 7 2024-12-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 173.200 - 173.284 84.000 29.9101970000, 78.8026220000 Estimation Done 8 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 173.300 - 173.376 76.000 29.9093820000, 78.8025230000 Estimation Done 10 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 174.200 - 174.228 28.000 29.9048700000, 78.7940690000 Estimation Done 9 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 174.300 - 174.364 64.000 29.9048870000, 78.7933070000 Estimation Done 7 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 174.400 - 174.420 20.000 29.0000000000, 78.0000000000 Estimation Done 9 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 175.850 - 175.942 92.000 29.8989030000, 78.7932510000 Estimation Done 8 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 176.010 - 176.082 72.000 29.8980920000, 78.7893640000 Estimation Done 7 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 176.600 - 176.656 56.000 29.8951730000, 78.7842880000 Estimation Done 10 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 180.000 - 180.040 40.000 29.9006080000, 78.7631360000 Estimation Done 10 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 180.041 - 180.057 16.000 29.9008530000, 78.7629280000 Estimation Done 10 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 180.070 - 180.086 16.000 29.9007490000, 78.7627070000 Estimation Done 10 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 180.600 - 180.672 72.000 29.9010080000, 78.7624580000 Estimation Done 8 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 181.600 - 181.656 56.000 29.9069450000, 78.7659180000 Estimation Done 9 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[62] Late Shri Geetaram Pokhriyal state highway (Marchula Saraikhet Baijro Pokhra Satpuli Pauri state highway) Crash barrier 181.750 - 181.794 44.000 29.9066730000, 78.7652960000 Estimation Done 9 2024-01-27 00:00:00 installed under Roads safety Dec 2024
[3446] Bidoli Ghunna motor road Scupper 0.125 -- 30.1242700000, 78.9028500000 scupper Jan 2024
[3446] Bidoli Ghunna motor road Scupper 0.325 -- 30.1236300000, 78.9032600000 scupper Jan 2024
[3446] Bidoli Ghunna motor road Scupper 0.500 -- 30.1227800000, 78.9042400000 scupper Jan 2024
[3446] Bidoli Ghunna motor road Scupper 0.625 -- 30.1226600000, 78.9049300000 scupper Jan 2024
[3446] Bidoli Ghunna motor road Scupper 0.650 -- 30.1225700000, 78.9054100000 scupper Jan 2024
[3446] Bidoli Ghunna motor road Scupper 0.750 -- 30.1227100000, 78.9057100000 scupper Jan 2024
[3446] Bidoli Ghunna motor road Scupper 1.025 -- 30.1241000000, 78.9042900000 scupper Jan 2024
[3446] Bidoli Ghunna motor road Scupper 1.175 -- 30.1246100000, 78.9056600000 scupper Jan 2024
[3446] Bidoli Ghunna motor road Scupper 1.275 -- 30.1253600000, 78.9049900000 scupper Jan 2024
[3446] Bidoli Ghunna motor road Scupper 1.500 -- 30.1254500000, 78.9042000000 scupper Jan 2024
[3446] Bidoli Ghunna motor road Scupper 1.625 -- 30.1262200000, 78.9051200000 scupper Jan 2024
[3446] Bidoli Ghunna motor road Scupper 1.700 -- 30.1257200000, 78.9052100000 scupper Jan 2024
[3446] Bidoli Ghunna motor road Scupper 1.900 -- 30.1258100000, 78.9027300000 scupper Jan 2024
[3446] Bidoli Ghunna motor road Scupper 2.100 -- 30.1245700000, 78.9061500000 scupper Jan 2024
[3446] Bidoli Ghunna motor road Scupper 2.275 -- 30.1242000000, 78.9065300000 scupper Jan 2024
[3446] Bidoli Ghunna motor road Scupper 2.400 -- 30.1247400000, 78.9077700000 scupper Jan 2024
[3446] Bidoli Ghunna motor road Scupper 2.500 -- 30.1234600000, 78.9085300000 scupper Jan 2024
[3446] Bidoli Ghunna motor road Scupper 2.750 -- 30.1223500000, 78.9079800000 scupper Jan 2024
[3446] Bidoli Ghunna motor road Parapet 0.050 -- 30.1248600000, 78.9023900000 Parapet (Plum) Jan 2024
[3446] Bidoli Ghunna motor road Parapet 1.400 -- 30.1252600000, 78.9036400000 Parapet (plum) Jan 2024
[54] Karanprayg Nauti Paithani state highway Slide Zone 58.000 - 58.200 200.000 30.1768487000, 79.0800382000 Estimation Done 10 Jan 2024